w/c 11th March 2019

  • Project Team Conference Calls
    • Monday 11th March - UAT signed-off and confirmed go-live for Wednesday 13th March .  GoCAB subsequently advised 
    • Wednesday 13th March - various points throughout the day to monitor progress
    • Thursday 14th March - weekly project team conference call
  • Application Webservers - Live 
    • All urls checked via the live Load Balancers to be ok with the following exceptions 
      • Kx parcels – live config file required  - subsequently received from TB

      • Internal booking – issue with EIT 

      • External booking – currently displaying a 302 error - subsequently resolved 

    • As part of the preparation of the live deployment  (ref I190311-1591)

      • TTL will reduced overnight on the 11th March 
      • ITI support confirmed for Wednesday 13th March 
    • Live Deployment commenced Wednesday 13th March at 9.30 a.m.
      • At close of play 8 out 9 websites have been signed-off 
      • The remaining Issue regarding  with the Student MyAccommodation site via MyEd was resolved early Thursday morning and signed-off
      • All websites confirmed as running on Thursday 14th March
      • Subsequently on 15th March
        • Issue subsequent report with EIT process - now resolved
        • Issue processing credit cards via Kx Registrations
        • Issue with tablets syncing on Kx Inspections 
  • Nexus
    • Nessus scans have been set up for the new web and db servers, - No high/medium/low severities found.
  • Windows services 
    • Analysis of services on both Test and live supplied by TB
  • Project plan updated and circulated 
  • JIRA's updated 