Report for March 2019

 
Report by Muriel Mewissen for  Sheila Fraser (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)
and Jim Nisbet (MVMBUS Programme Owner), Philippa Burrell (MVMLAT Programme Owner), and Charles ffrench-Constant and Paul McGuire (MVMRes Programme Owners)

 

Portfolio Commentary, RAG and Resources Update

Commentary:

During March, three projects completed successfully:

This takes the number of ongoing projects across the portfolio down to 14, eight projects are managed by Project Services PMs.

All projects are reporting a GREEN or AMBER RAG status, there is no RED project.

The monthly reports for the programmes are available below:

IS Apps Resources to end March 2019

NB: The chart below only shows IS Apps resources.

CMVM had a budget of 150 ring fenced days for 18/19:

 

Forward Look - March 2019