Report for December 2019

 

Report by Muriel Mewissen for Sheila Fraser (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)
and Jim Nisbet (MVMBUS Programme Owner), Philippa Burrell (MVMLAT Programme Owner), and Charles ffrench-Constant and Paul McGuire (MVMRes Programme Owners)

Portfolio Commentary, RAG and Resources Update

Commentary:

During December, we note that Practique was successfully used to support the first online admission exams for MBChB in early December. A two news items were published on MVM136 Practique Roll-Out:

The most active project remains MVM316: Fragile X Registry website where final developments were successfully delivered this month. These will go LIVE and the website can will be launched following successful penetration tests scheduled for early January. The project is expected to close in January.

The monthly reports for the programmes are available below:

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

IS Apps Resources to end December 2019

NB: The chart below only shows IS Apps resources.

CMVM had a budget of 150 ring fenced days for 19/20 which has been allocated as such:

 

Forward Look - December 2019