August 2015
- Report Date
- August 2015
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
During August
In commencing the prgramme for 2015-16, the overal project budget has been set at 246 days with regards to the following programme activity;
Project Code | Description | Days |
ACSP01 | Programme Related activity for Accommodation Services | 6 |
ACS033 | Student Application - Enhanced Student Data Feed Project continued from 2014-15 | 8 |
ACS034 | UniWare Cashless Catering Project continued from 2014-15 | 2 |
AP56-056 | Upgrade Kx Test Infrastructure | 50 |
AP56-057 | Booking Agent Interface | 10 |
AP56-058 | Migration of Kx to Cloud Environment | 100 |
AP56-059 | Delivered Catering External | 30 |
ACSPB2 | Balance Row - Sponsored Funded equates to 20% for sponsor funded projects approved for 2015-16 | 40 |
Total | 246 |
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP56-056 Upgrade Kx Test Infrastructure Funded Planning: October 2015 Delivery: March 2016 | Plan This project has been declared as part of the annual planning process . - project to commence in October 2015 - initial planning phase scheduled to be completed in November 2015 - delivery date scheduled for March 2016 Dependencies - will require a large commitment from Accommodation Services team to oversee user acceptance testing - will require a significant input from IS Applications Development Technology team in preparing the new infrastructure - requirement to understand any potential impacts if a Kx upgrade is scheduled through this period |
AP56-057 Booking Agent Interface Funded Planning: September 2015 Delivery: February 2016 | Plan This project has been declared as part of the annual planning process . - project to commence in September 2015 - initial planning phase scheduled to be completed in October 2015 - delivery date scheduled for February 2016 Dependencies - largely dependant on supplier delivering module - will require a large commitment from Accommodation Services team to oversee user acceptance testing - will require input from IS Applications Development Technology team to assist with systems integration |
AP56-058 Migration of Kx to Cloud Environment Funded Planning: January 2016 Delivery: July 2016 | Plan This project has been declared as part of the annual planning process . - project to commence in January 2016 - initial planning phase scheduled to be completed in January 2016 - delivery date scheduled for July 2016 Dependencies - totally dependant on supplier hosting capability - will require a large commitment from Accommodation Services team to oversee user acceptance testing - will require input from IS Applications Development Technology team to assist with systems integration and performance testing |
AP56-059 Delivered Catering External Funded Planning: January 2016 Delivery: May 2016 | Plan This project has been declared as part of the annual planning process . - project to commence in January 2016 - initial planning phase scheduled to be completed in January 2016 - delivery date scheduled for May 2016 Dependencies - totally dependant on supplier delivering new application module - will require a large commitment from Accommodation Services team to oversee user acceptance testing - will require input from IS Applications Development Technology team to assist with systems integration |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||
Student Application - Enhanced Student Data Feed Discretionary Milestones
RAG Status Green | Report by Colin Forrest for August 2015
Achievements in the Last Period
Issues
Next steps
| ||||||||||
UniWare Cashless Catering Discretionary Milestones
RAG Status Blue | Report by Andrew Stewart for August 2015
Achievements in the last period
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risks | Rag Status | Risk Owner |
30/06/15 | 1 | Unable to commence scheduled project - Migration of Kx to Cloud Environment | Red | Claire Barnish |
30/06/15 | 2 | Unable to commence scheduled project Delivered Catering External | Red | Claire Barnish |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2014-15
Date | Comments |
16/09/15 | Minutes from Programme Meeting |