During August

In commencing the prgramme for 2015-16, the overal project budget has been set at 246 days with regards to the following programme activity;

Project CodeDescriptionDays
ACSP01Programme Related activity for Accommodation Services6
ACS033

Student Application - Enhanced Student Data Feed

Project continued from 2014-15

8
ACS034

UniWare Cashless Catering

Project continued from 2014-15

2
AP56-056Upgrade Kx Test Infrastructure50
AP56-057Booking Agent Interface10
AP56-058Migration of Kx to Cloud Environment100
AP56-059Delivered Catering External30
ACSPB2

Balance Row - Sponsored Funded

equates to 20% for sponsor funded projects approved for 2015-16

40
Total 246

 

The planned activity regarding active projects throughout SEptember was very limited, with the main activity associated with the amended feed from the Student System.

During October, there will be the requirememnt to determine feasibility of commencing the following projects;

  • AP56-056: Upgrade Kx Test Infrastructure
  • AP56-057: Booking Agent Interface

Additionally there is the requirement to consider any further projects for 2016-17 and beyond as part of the annual planning activity according to the issued timetable  

 

 

 

 

Section Two: Projects Not Started

 

The scheduled projects for 2015-16 are

 

Project InfoProgramme Managers Commentary

AP56-056

Upgrade Kx Test Infrastructure

Funded

Planning: October 2015

Delivery: March 2016

Plan

This project has been declared as part of the annual planning process .

- project to commence in October 2015

- initial planning phase scheduled to be completed in November 2015

- delivery date scheduled for March 2016

Dependencies

will require a large commitment from Accommodation Services team to oversee user acceptance testing

- will require a significant input from IS Applications Development Technology team in preparing the new infrastructure

- requirement to understand any potential impacts if a Kx upgrade is scheduled through this period

AP56-057

Booking Agent Interface

Funded

Planning: September 2015

Delivery: February 2016

Plan

This project has been declared as part of the annual planning process .

- project to commence in September 2015

- initial planning phase scheduled to be completed in October 2015

- delivery date scheduled for February 2016

Dependencies

- largely dependant on supplier delivering module

- will require a large commitment from Accommodation Services team to oversee user acceptance testing

- will require input from IS Applications Development Technology team to assist with systems integration

AP56-058

Migration of Kx to Cloud Environment

Funded

Planning: January 2016

Delivery: July 2016

Plan

This project has been declared as part of the annual planning process .

- project to commence in January 2016

- initial planning phase scheduled to be completed in January 2016

- delivery date scheduled for July 2016

Dependencies

- totally dependant on supplier hosting capability

- will require a large commitment from Accommodation Services team to oversee user acceptance testing

- will require input from IS Applications Development Technology team to assist with systems integration and performance testing

AP56-059

Delivered Catering External

Funded

Planning: January 2016

Delivery: May 2016

Plan

This project has been declared as part of the annual planning process .

- project to commence in January 2016

- initial planning phase scheduled to be completed in January 2016

- delivery date scheduled for May 2016

Dependencies

- totally dependant on supplier delivering new application module

- will require a large commitment from Accommodation Services team to oversee user acceptance testing

- will require input from IS Applications Development Technology team to assist with systems integration

Section Three: Projects in Progress

 

 

 

 

Project InfoProject Managers Commentary

ACS033

Student Application - Enhanced Student Data Feed

Discretionary

Milestones

27-Nov-2015 ASOR (Acceptance Sign Off) UoE Work    
29-Jan-2016 Deployment    
12-Feb-2016 DSOR (Delivery Sign Off)    
26-Feb-2016 Close  

RAG Status

Green

Report by Colin Forrest for September 2015

Achievements in the last period

  • The feed has been updated to the specification agreed between SSP, Accommodation Services and the third party supplier Kx
  • That updated feed has been integrated into the TEST environment.

Issues

  • None

Next steps

  • The 3rd party supplier Kx will configure their system to the agreed feed through October.
  • UAT will then be done through November with a Production launch scheduled for January.

 

 

ACS034

UniWare Cashless Catering

Discretionary

Milestones

Target dateTitle
  
30-Oct-2016Closure

RAG Status

Blue

Report by Andrew Stewart for September 2015

 

Achievements in the last period

  • The neccessary procedures to decommission Counter Solutions have been documented and reviewed with IS Applications

 

Issues

  • The project manager has been not been able to organise the remaining decommission work
  • Due to conflicting priorities regarding other Estates projects, the project manger has not been able to prepare the closure report

 

Next steps

  • Complete the decommission process relating to Counter Solutions on all three environments of Dev, Test and Live
  • Prepare the closure report, including the an overview of the activities resulting in the budget overspend (as discussed at the last programme meeting)
  • Project closure

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary
  

 

Section Five: Programme Risks

DateRisk Ref.Programme RisksRag StatusRisk Owner
30/06/151Unable to commence scheduled project - Migration of Kx to Cloud EnvironmentRedClaire Barnish
30/06/152Unable to commence scheduled project Delivered Catering ExternalRedClaire Barnish

Section Six : Programme Meeting Minutes

 This section details the minutes from the programme meetings held in 2014-15

DateComments
16/09/15Minutes from Programme Meeting