November 2015

Report Date
November 2015

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

During November,

In completing an overview of the programme with Accommodation Services the following actions have been noted;

  • It has been confirmed that the project AP56-057: Booking Agent Interface will be undertaken this academic year, with the start date being re-scheduled to February 2016
  • It has been confirmed that the project AP56-059: Delivered Catering will commence this academic year, with the start date being re-scheduled to June 2016
  • The project AP56-056: Upgrade Kx Test Infrastructure has been withdrwawn (as this will now be undertaken in 2016-17)
  • The project AP56-058 Migration to Kx Cloud Environment  has been withdrawn
  • As a consequence of the above changes, the programme budget has been reduced from 246 days to 45 days for this academic year and the programme burn rate figures have dramtically altered.          A detailed breakdown of the changes is attached

In addition, the project ACS034: Uniware Cashless Catering has now been completed and closed.

 

 

 

Section Two: Projects Not Started

 

The scheduled projects for 2015-16 are

 

Project InfoProgramme Managers Commentary

AP56-057

Booking Agent Interface

Funded

Planning: January 2016

Delivery: April 2016

Plan

This project has been declared as part of the annual planning process .

- project scheduled to commence on at the start of February 2016

- initial planning phase scheduled to be completed by the end of February 2016

- delivery date scheduled for April 2016

Dependencies

- largely dependant on supplier delivering module

- will require a large commitment from Accommodation Services team to oversee user acceptance testing

- will require input from IS Applications Development Technology team to assist with systems integration

AP56-059

Delivered Catering External

Funded

Planning: June 2016

Delivery: t.b.c.

Plan

This project has been declared as part of the annual planning process .

- project to commence in June 2016

- initial planning phase scheduled to be completed in June 2016

- delivery date to be defined

Dependencies

- totally dependant on current supplier delivering new application module or an alternative product is procured

- will require a large commitment from Accommodation Services team to oversee user acceptance testing

- will require input from IS Applications Development Technology team to assist with systems integration

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

ACS033

Student Application - Enhanced Student Data Feed

Discretionary

Milestones

Target dateTitle
18-Dec-2015ASOR (Acceptance Sign Off) UoE Work
29-Jan-2016Deployment
12-Feb-2016DSOR (Delivery Sign Off)
26-Feb-2016Close

RAG Status

Amber

Report by Colin Forrest for Novembert 2015

Achievements in the last period

  • The Kx development plan has been approved.
  • the 20 users necessary to test the feed have been identified and are being setup.
  • We have resolved our JIRAs.. 

Issues

  • The additional work to create 20 test users and solve JIRAs will take the project 2 days over our reduced 40 day budget.  We will need to resolved/PICCL'd in the next period.  The business are aware and support our actions.

Next steps

  • Test the feed.

 

The project has been assigned a RAG status of Amber as there will be the requirement to increase the project budget

ACS034

UniWare Cashless Catering

Discretionary

Milestones

RAG Status

Blue

Report by Andrew Stewart for November 2015

 

Achievements in the last period

  •  The decommission process relating to Counter Solutions on all three environments of Dev, Test and Live has been completed
  • The project closure report has been approved
  • The project was formally signed-off by WIS on 4th December 2015

Issues

  • None

 

Next steps

  • None
  •  

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary
ACS034 - Uniware Cashless Catering

Project closed on 4th December 2015

Project Closure Report

AP56-056

Upgrade Kx Test Infrastructure

Project withdrawn on 4th December 2015

AP56- 058

Migration to Kx Cloud Environment 

Project withdrwan on 4th December 2015

 

Section Five: Programme Risks

DateRisk Ref.Programme RisksRag StatusRisk Owner
30/06/151

Unable to commence scheduled project - Migration of Kx to Cloud Environment

Risk closed after confirmation that project will not be undertaken this year

ClosedClaire Barnish
30/06/152

Unable to commence scheduled project Delivered Catering External

Rag Status adjusted from Red to Green after confirmation that the project is to progress

GreenClaire Barnish

Section Six : Programme Meeting Minutes

 This section details the minutes from the programme meetings held in 2014-15

DateComments
16/09/15Minutes from Programme Meeting
11/11/15Minutes from Programme Meeting
02/12/15Minutes from Programme Review Meeting