December 2015
- Report Date
- December 2015
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
During December,
From a programme perspective, there was the requirement to transfer 2 days from the sponsor funded contingency (ACSPB2) to cover the additional 2 days projected to complete ACS033. As a result, the sponsor funded contingency budget was reduced from 10 days to 8 days, with no overall change to the previously revised programme budget (in November) of 45 days.
Further to the mid-year review, the overall programme budget of 6 days is now close to being exceeded and will require to be discussed at the next programme meeting. In the interim a new programme risk (ref 3) has been recorded.
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP56-057 Booking Agent Interface Funded Planning: January 2016 Delivery: April 2016 | Plan This project has been declared as part of the annual planning process . - project scheduled to commence on at the start of February 2016 - initial planning phase scheduled to be completed by the end of February 2016 - delivery date scheduled for April 2016 Dependencies - largely dependant on supplier delivering module - will require a large commitment from Accommodation Services team to oversee user acceptance testing - will require input from IS Applications Development Technology team to assist with systems integration |
AP56-059 Delivered Catering External Funded Planning: June 2016 Delivery: t.b.c. | Plan This project has been declared as part of the annual planning process . - project to commence in June 2016 - initial planning phase scheduled to be completed in June 2016 - delivery date to be defined Dependencies - totally dependant on current supplier delivering new application module or an alternative product is procured - will require a large commitment from Accommodation Services team to oversee user acceptance testing - will require input from IS Applications Development Technology team to assist with systems integration |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||||||
Student Application - Enhanced Student Data Feed Discretionary Milestones
RAG Status Amber | Report by Colin Forrest for December 2015 Achievements in the last period
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
ACS034 - Uniware Cashless Catering | Project closed on 4th December 2015 Project Closure Report |
AP56-056 Upgrade Kx Test Infrastructure | Project withdrawn on 4th December 2015 |
AP56- 058 Migration to Kx Cloud Environment | Project withdrwan on 4th December 2015 |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risks | Rag Status | Risk Owner |
30/06/15 | 1 | Unable to commence scheduled project - Migration of Kx to Cloud Environment Risk closed after confirmation that project will not be undertaken this year | Closed | Claire Barnish |
30/06/15 | 2 | Unable to commence scheduled project Delivered Catering External Rag Status adjusted from Red to Green after confirmation that the project is to progress | Green | Claire Barnish |
05/01/16 | 3 | Programme Management Budget being exceeded | Green | Andrew Stewart |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2014-15
Date | Comments |
16/09/15 | Minutes from Programme Meeting |
11/11/15 | Minutes from Programme Meeting |
02/12/15 | Minutes from Programme Review Meeting |