March 2016
- Report Date
- March 2016
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
During March
There is currently little activity being undertaken within the programme at this time;
- The revised student feed generated through teh project ACS033 has been successfully deployed to the Live environment
- The new project, ACS035 Booking Agent Interface has currently stalled whilst awaiting clarification of technical requirements
The overall programme budget of 7 days has now been exceeded by 1 day and the programme manager has estimated a further 1 days effort will be required for the remainder of the year , as programme activity is now very light. Further discussions to be held with the CSG Portfolio Manager to resolve this deficit.
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP56-059 Delivered Catering External Funded Planning: June 2016 Delivery: t.b.c. | Plan This project has been declared as part of the annual planning process . - project to commence in June 2016 - initial planning phase scheduled to be completed in June 2016 - delivery date to be defined Dependencies - totally dependant on current supplier delivering new application module or an alternative product is procured - will require a large commitment from Accommodation Services team to oversee user acceptance testing - will require input from IS Applications Development Technology team to assist with systems integration |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||
Student Application - Enhanced Student Data Feed Discretionary Milestones
RAG Status Amber | Report by Colin Forrest for March 2016Achievements in the last period
Issues
Next steps
| ||||
ACS035 (AP56-057) Booking Agent Interface Funded Milestones Planning date 24/04 (was 11/03) RAG Status Amber | Report by Chris Lawford for March 2016Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
ACS034 - Uniware Cashless Catering | Project closed on 4th December 2015 Project Closure Report |
AP56-056 Upgrade Kx Test Infrastructure | Project withdrawn on 4th December 2015 |
AP56- 058 Migration to Kx Cloud Environment | Project withdrwan on 4th December 2015 |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risks | Rag Status | Risk Owner |
30/06/15 | 2 | Unable to commence scheduled project Delivered Catering External Rag Status adjusted from Red to Green after confirmation that the project is now scheduled to commence in June. | Green | Claire Barnish |
05/01/16 | 3 | Programme Management Budget being exceeded Rag Status currently at Amber untill further discussions held with CSG Portfolio Manager | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2014-15
Date | Comments |
16/09/15 | Minutes from Programme Meeting |
11/11/15 | Minutes from Programme Meeting |
02/12/15 | Minutes from Programme Review Meeting |