April 2016

Report Date
April 2016

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

As a result of the project activity through April, there are currently no active projects within the programme having closed the project ACS033 - Student Application - Enhanced Student Data Feed and withdrawing the project ACS035 - Booking Agent Interface having determined that the activity could be catered for within the Applications Support environment.

The programme manager attended the latest meeting with the Kinetics’ account manager along with representatives from Accommodation Services

A number of budget changes relating to the previously active projects has resulted in the overall programme budget being reduced from 47 days to 31 days due to

  • ACS033 - An additional 4 days was required to complete the project
  • ACS035 - The full 20 days projected effort has been withdrawn.  The minimal time utilised has been transferred to the overall programme account.

The overall programme budget of 6 days has now been exceeded by 2.5 days and the programme manager has estimated a further 0.5  days effort will be required for the remainder of the year , as programme activity is now very light. Further discussions to be held with the CSG Portfolio Manager to resolve this deficit.

The remaining project, Delivered Catering External,  was scheduled to commence in June 2016, will most likely be delayed until late 2016

 

 

Section Two: Projects Not Started

 

The scheduled projects for 2015-16 are

 

Project InfoProgramme Managers Commentary

AP56-059

Delivered Catering External

Funded

Planning: June 2016

Delivery: t.b.c.

Plan

This project has been declared as part of the annual planning process .

- project to commence in June 2016

- initial planning phase scheduled to be completed in June 2016

- delivery date to be defined

Dependencies

- totally dependant on current supplier delivering new application module or an alternative product is procured

- will require a large commitment from Accommodation Services team to oversee user acceptance testing

- will require input from IS Applications Development Technology team to assist with systems integration

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

ACS033

Student Application - Enhanced Student Data Feed

Discretionary

 

 

RAG Status

Blue

Report by Colin Forrest for April 2016

 

Achievements in the last period

  • The project has been delivered and closed
  • The stakeholders are happy that the project has delivered an enhanced feed that will benefit Accommodation Services.
  • The project closure report was circulated and approved by the project sponsor enabling the project to be closed

Issues

  • The following operational issues were noted post go-live and will require process changes to be implemented within the Kx environment.  In reviewing the issues, all were attributable to the manner in which data from the student systems has been interpreted.
    • Students with the statusApplicants from Other Admissions’ currently cannot apply for accommodation
    • Cancelled – Deferred’ status students currently cannot apply for accommodation
    • New Entrant not yet matriculated/New entrant still to be matriculated’ students cannot apply for accommodation
    • International Status/Fee Status - some international students have been wrongly advised regarding accommodation provision

Next steps

  • None

ACS035 (AP56-057)

Booking Agent Interface

Funded

 

RAG Status

Blue

Report by Chris Lawford for April 2016

 

Achievements in Last Period

  • Project Withdrawn. Any activities in support of third party project will be undertaken by production support.
  • The time associated with this project has been moved to the programme account

Issues

  • In an effort to confirm that there were no unknown technical barriers to implementing the new business application, a request to clarify technical requirements with the supplier was requested.  However, a delay in organising a teleconference call with the supplier delayed the above decision by around 6 weeks

Next steps

  • None

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary
ACS034 - Uniware Cashless Catering

Project closed on 4th December 2015

Project Closure Report

AP56-056

Upgrade Kx Test Infrastructure

Project withdrawn on 4th December 2015

AP56- 058

Migration to Kx Cloud Environment 

Project withdrawn on 4th December 2015

 

Section Five: Programme Risks

DateRisk Ref.Programme RisksRag StatusRisk Owner
30/06/152

During the programme meeting on 18/05/16, the programme owner advised that this project would not commence this year.  As a rseult, the risk has now been closed.

Closed 
05/01/163

Programme Management Budget being exceeded

Rag Status currently at Amber untill further discussions held with CSG Portfolio Manager

AmberAndrew Stewart

Section Six : Programme Meeting Minutes

 This section details the minutes from the programme meetings held in 2014-15

DateComments
16/09/15Minutes from Programme Meeting
11/11/15Minutes from Programme Meeting
02/12/15Minutes from Programme Review Meeting
18/05/16Minutes from Programme Meeting