Section One: Programme Commentary, RAG and Resources Update
There will be no further project activity within the programme this year after the decision to re-schedule the start date of the Delivered Catering External to next year.
The overall programme budget of 6 days has now been exceeded by 2.5 days and the programme manager has estimated a further 0.5 days effort will be required for the remainder of the year , as programme activity is now very light. Further discussions to be held with the CSG Portfolio Manager to resolve this deficit.
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP56-059 Delivered Cajavascript:void('Delete Rows')tering External Funded Planning: early 16/17 Delivery: t.b.c. | Plan This project has been declared as part of the annual planning process . - project has now been re-scheduled to commence in 2016/17 - initial planning phase scheduled to be completed in 2016/17 - delivery date to be defined Dependencies - totally dependant on current supplier delivering new application module or an alternative product is procured - will require a large commitment from Accommodation Services team to oversee user acceptance testing - will require input from IS Applications Development Technology team to assist with systems integration |
Section Three: Projects in Progress
Project Info | Project Managers Commentary |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
ACS034 - Uniware Cashless Catering | Project closed on 4th December 2015 Project Closure Report |
AP56-056 Upgrade Kx Test Infrastructure | Project withdrawn on 4th December 2015 |
AP56- 058 Migration to Kx Cloud Environment | Project withdrawn on 4th December 2015 |
ACS033 Student Application - Enhanced Student Data Feed | Project closed on 29th April 2016 Project Closure Report |
ACS035 Booking Agent Interface | Project withdrawn on 22nd April 2016 |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risks | Rag Status | Risk Owner |
05/01/16 | 3 | Programme Management Budget being exceeded Rag Status currently at Amber untill further discussions held with CSG Portfolio Manager | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2014-15
Date | Comments |
16/09/15 | Minutes from Programme Meeting |
11/11/15 | Minutes from Programme Meeting |
02/12/15 | Minutes from Programme Review Meeting |
18/05/16 | Minutes from Programme Meeting |