July 2016 Report

Report Date
July 2016

     

Report for July 2016

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

 

Section One: Programme Commentary, RAG and Resources Update

 

An initial project planning meeting for 2016-17 has been scheduled for 15th August.  Initial indications are that there are no hard deadlines regarding any of the projects scheduled for next year.

 

Forward Look and RAG for July 2016

 

Resource Position to 31st July 2016

 

 

Section Two: Projects Not Started

 

The scheduled projects for 2016-17 are:

 

Project InfoProgramme Managers Commentary

AP56-059

Delivered Catering External

Funded

Planning: early 16/17

Delivery: t.b.c.

Plan

This project has been declared as part of the annual planning process .

- project has now been re-scheduled to commence in 2016/17

- initial planning phase scheduled to be completed in 2016/17

- delivery date to be defined

Dependencies

- totally dependant on Accommodation Services identifying a suitable solution 

- may require an interface with the UoE central finance system

- will require a large commitment from Accommodation Services team to oversee user acceptance testing

- will require input from IS Applications Development Technology team to assist with systems integration

AP67-046

Kx Database Infrastructure Upgrade

Funded

Planning: early 16/17

Delivery: t.b.c.

Plan

This project has been declared as part of the annual planning process .

- initial planning phase scheduled to be completed in 2016/17

- delivery date to be defined

Dependencies

- totally dependant on current supplier delivering new application module or an alternative product is procured

- will require a large commitment from Accommodation Services team to oversee user acceptance testing

- will require input from IS Applications Development Technology team to assist with systems integration

AP67-047

Cahless Catering Phase 2

Planning: early 16/17

Delivery: t.b.c.

Plan

This project has been declared as part of the annual planning process .

- initial planning phase scheduled to be completed in 2016/17

- delivery date to be defined

Dependencies

- totally dependant on current supplier delivering new application module or an alternative product is procured

- will require a large commitment from Accommodation Services team to oversee user acceptance testing

- will require input from IS Applications Development Technology team to assist with systems integration

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary
No projects in progress 

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary
ACS034 - Uniware Cashless Catering

Project closed on 4th December 2015

Project Closure Report

AP56-056

Upgrade Kx Test Infrastructure

Project withdrawn on 4th December 2015

AP56- 058

Migration to Kx Cloud Environment 

Project withdrawn on 4th December 2015

ACS033

Student Application - Enhanced Student Data Feed

Project closed on 29th April 2016

Project Closure Report

ACS035

Booking Agent Interface

Project withdrawn on 22nd April 2016

 

Section Five: Programme Risks

DateRisk Ref.Programme RisksRag StatusRisk Owner
08/07/163

Programme Management Budget being exceeded

Rag Status currently at Amber untill further discussions held with CSG Portfolio Manager

AmberAndrew Stewart

Section Six : Programme Meeting Minutes

 This section details the minutes from the programme meetings held in 2014-15

DateComments
16/09/15Minutes from Programme Meeting
11/11/15Minutes from Programme Meeting
02/12/15Minutes from Programme Review Meeting
18/05/16Minutes from Programme Meeting