Report for January 2019
- Report Date
- January 2019
During January,
- Work on the Kx Infrastructure project continues. the project is currently running around two weeks behind the original schedule due to unexpected technical issues encountered during the testing of Application Webservers via teh Load Balancers
- Initial project proposals have been received for the next Annual planning round. The programme manager will look to arrange an estimation meeting before the end of February
Discussions
- Regarding the strategy around the Delivered Catering procurement is on-going
Forward Look
Resource Position
Section Two: Projects Not Started
The scheduled projects for 2018-19 are:
Project Info | Programme Managers Commentary |
AP89-901 Salto Door Access Funded Planning: April 2020 Delivery: October 2020
|
Plan This project has been declared as part of the annual planning process for 2018-19, but has been deferred to Q3 2019 until the Network Replacement project is more advanced Dependencies: - On the availability of the ACE technical lead - will require input from IS Applications Development Technology and IS Applications Production Management |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||
Kx Infrastructure Consolidation Category: Discretionary Sponsor Funded
Milestones have been re-planned
RAG Status: Amber |
Report by Andy Stewart for January 2019 Achievements in the last period
Issues
Next steps
RAG CommentaryThe project having been re-planned, is currently two weeks behind schedule due to issues experienced during Load Balancer testing . Any further delays could impact on the business having the necessary time period to implement the Kx2018 software upgrade prior to the summer business activity |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Section Five: Programme Risks
Date Updated | Risk Ref. | Programme Risks | RAG Status | Risk Owner |
08/01/19 | 7 | Completion of Programme Activity within 2018-19 | Green | Andrew Stewart |
07/12/18 | 8 | Programme Management budget for 2018-19 being exceeded | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site
Attachment | Size |
---|---|
aceoct18.png | 34.17 KB |
aceoct2.png | 29.72 KB |
201810-rag.png | 25.71 KB |
201811-rag.png | 28.78 KB |
201811-resources.png | 20.87 KB |
201812b-rag.png | 29.32 KB |
201812-resources.png | 21.22 KB |
2019-rag.png | 28.27 KB |
201901-resources.png | 25.66 KB |