Report for July 2021
- Report Date
- July 2021
During July,
Work continues with the Delivered Catering Implementation project
Receivables integration with People and Money -
- Initial testing has been completed utilising the new charge types on the Kx environment
- UoE development has continued with the data extract from Kx
- Initial development has been completed and initial testing completed
- WSO2 development has yet to commence
- There is currently one outstanding question regarding the re-processing of rejected data transactions which is currently being investigated
Forward Look
Resource Position
Section Two: Projects Not Started
Project Info | Programme Managers Commentary |
|
No projects to be started |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||
Delivered Catering Implementation Category: Discretionary Sponsor Funded
Rag Status: Amber |
Report by Andy Stewart for July 2021 Achievements This Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
ACS042 - Delivered Catering Procurement |
Project closed on 28/05/21 |
Section Five: Programme Risks
The Risk 9 - Programme Management budget for 2019-20 being exceeded has been closed - programme budget not exceeded for the year
Date Updated | Risk Ref. | Programme Risks | RAG Status | Risk Owner |
20/07/21 | 11 |
Disruption from the current Novel coronavirus (Covid-19) outbreak |
Green | Andrew Glass |
20/07/21 | 12 | ACE System Integrations with People and Money | Amber | Andrew Glass |
Section Six : Programme Meeting Minutes
The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site