Report for January 2017

Report Date
January 2017

Report compiled by Tim Gray, IS Apps Programme Manager for Alex Carter  (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

Programme Commentary

aIn this short reporting period work has progressed on all projects. An options appraisal for Personalised Email for Students and Alumni has been written. This document will inform the implementation and allow planning to complete in the next reporting period. The rollout of "Timetable on my Phone" has competed planning and on schedule to bring in the next big batch of students at the start of semester 2. 

RAG Status and Forward Look

Resource Summary

 Section Two: Projects Not Started

Project Info Project Manager's Commentary

AP67-005 COM BI Annual Service Pack

Scheduled to start in the new year
AP67-004 COM Annual Wiki Upgrade Scheduled to start in Jan/Feb
AP67-9xx Upgrade to Exchange 2016  New in year project that will use the days from COM028

 

Section Three: Projects in Progress

Project Info Project Manager's Commentary

COM027

Enterprise Data Services Roll Out

Discretionary

Milestones

Target Datesort descending Title
31 Mar 2017 (indicative) Closure

RAG

GREEN

Report by Chris Copner for January 2017

Achievements in Last Period

  • Project successfully delivered scope of work outlined in the Project Brief
  • Deployment Review of the deployed Events Booking API completed and signed off on schedule

Issues

  • PICCL 9 - milestones change approved by WIS 3/2 - decision to use remaining budget to undertake a number of enhancements prior to closing project

Next Steps

  • Estimate remaining enhancements
  • Deliver prioritised enhancements
 

COM029

EDW Delivery

Discretionary

Milestones

Target Datesort descending Title
28-Feb-2017 Build Review - Proof of Concept
08-Mar-2017 Integration Review - Proof of Concept
16-Mar-2017 Delivery - Proof of Concept
24-Mar-2017 Closure - Proof of Concept

RAG

GREEN

Report by Chris Copner for January 2017

Achievements in Last Period

  • Build in progress
  • Two design sprints completed - these have enabled designs to be confirmed for staging layer to foundation layer and foundation layer to access layer

  • DEV environment build complete

  • Developer resourcing agreed

  • Design review complete

Issues

  • Change Item 5 - Change to scope and revised milestones - approved by WIS 3/2
  • Data capture is not supported in Oracle 12c - Oracle GoldenGate is required.  This will be a consideration in a future operational deployment [see JIRA COM029-22] [issue 4 added to PICCL]
  • Lack of certainty about how long it will take to map data to the foundation layer (this new risk has been added to the risk log as risk 9 and has been largely mitigated by the recent design sprints)

Next Steps

  • Update design documents with outputs from design sprints
  • Meeting to review security aspects of TAD with information security consultant - scheduled for 10/2
  • Create BI Universe on top of the star schemas to assist with testing the reports
  • Complete build
  • Project review of design and build by SSIS SME
  • External review of build by EDW consultant (to be scheduled for end Feb / start Mar)
  • Demonstration of working EDW model
 

COM030

Document Management for IS HR

Discretionary

Milestones

27-Jan-2017 Closure

RAG

GREEN

Report by Tim Gray for December 2016

Achievements in the last period

  • Some progress made on archiving process
  • Deployment Review Milestone completed 

Issues

  • No new issues to report

Next steps

  • Complete documentation of archiving process
  • Update user documentation on site
  • Draft closure report
  • Close project

COM031

Serengeti Document Managment Server Upgrade

Compliance

Milestones

15-Feb-2017 Build
01-Mar-2017 Integration
20-Mar-2017 Acceptance
27-Mar-2017 Deploy to Live
04-Apr-2017 Deployment review
26-Apr-2017 Upgrade Oracle CH
12-May-2017 Close

RAG

GREEN

Report by Sue Woodger for December 2016

Achievements

  • The Dev environment has been re-built and Netcall will be installing v6.8 wb 6 February

 Issues

  • On building the Dev environment developers ran into issues which interfered with the install and which were traced back to system updates that were completed in July which were originally installed in the wrong place on Dev by a temporary member of staff. Discussions with Unix resulted in a recommendation to rebuild Dev. This caused a delay to the build plus we were also delayed as we also had to renegotiate Netcalls time after the rebuild.

Next Steps

  • Build sign off by 15 February

COM032

Rollout Academic Timetable Integration with Office 365 Calendar

Discretionary

Milestones

Target Datesort descending Title
30-Jan-2017 Delivery - Deployment of MyEd Portlet (with Opt-Out)
15-Feb-2017 Deployment Review - MyEd Portlet (with Opt-Out)
28-Feb-2017 Deployment Review - rollout of timetables to all students
17-Apr-2017 Closure

RAG

GREEN

 

Report by Chris Copner for January 2017

Achievements in Last Period

  • Successful roll-out of Timetable on my Phone to 1st year students
  • UAT of self-service opt-out portlet complete
  • New live RDB signed off

Issues

  • None in this reporting period

Next Steps 

  • Roll-out to remaining students scheduled for February
  • Deployment of MyEd Portlet (with Opt-Out)
  • Deployment Review - MyEd Portlet (with Opt-Out)
  • Deployment Review - rollout of timetables to all students
 

COM033 Personalised Email for Students and Alumni

Discretionary

Milestones

Milestones have still to be agreed.

RAG

AMBER

Report by Karen Stirling January 2017

Achievements in Last Period

  • Options Paper reviewed with Stakeholders - EUSA, Students Systems

Issues

  • Delay in planning  due to Recommended Option 1 unable to gain resource approval from Student Systems to develop this option, due to their commitment on other projects
  • Decision agreed to take forward next best option (2) - Generate name based emails in IDM
  • Project manager is currently on sick leave,  however the project has allocated a stand-in Project Manager over this period to help progress planning

Next Steps 

  • Complete planning, estimation and project brief
  • Complete requirements gathering

The project status is AMBER due to delays in gaining agreement on which option can be progressed.

 

 

DTO001 Digital Transformation Website

Discretionary

Milestones

20-Jan-2017 Planning Sign-off

RAG

GREEN

Achievements in Last Period

  •  Project initiated and initial discussions with stakeholders conducted
  • Project brief drafted as far as possible
  • Meetings with Web teams to discuss design & content arranged

Issues and Risks

  • None reported

​Next Steps

  • Complete project brief
  • Commence work on design (based on consultations)
  • Deliver prototype of website

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

COM026

Wiki Upgrade

Discretionary

 

Report by Tim Gray

This project was closed on 23/09/16  (WIS Notes 23/09/16)

Please see the Completion Report for further information

COM025

BI Architechture

Discretionary

Report by Craig Middlemass

This project was closed on 04/11/16  (WIS Notes 04/11/16)

Please see the Completion Report for further information

COM028

Upgrade onsite Exchange Mail Relay Servers

Discretionary

Report by Chris Copner

This project was closed on 11/11/16 (WIS Notes 11/11/16)

Please see the Completion Report for further information

COM022 Academic Timetable Integration into Office 365 Calendar  

Discretionary

Report by Chris Copner

This project was closed on 18/11/16  (WIS Notes 18/11/16)

Please see the Completion Report for further information

Section Five: Actions/Notes from monthly meeting held on 12/12/2016

 

Project Action / Notes Responsibility Status
       
New project? There are several small pieces of work that need to be managed but not large enough to justify a stand alone project. AC suggested we could have a bucket project where these tasks could reside. AC to advise on budget. Alex Carter Open