Programme Commentary

The long-running COM036 has now been closed, and COM041 is now due to be closed at the end of May. There is a short delay to this because of PM availability to work on the closure. The decommissioning tasks for COM036 (not completed) have been picked up under INF137. This month also saw the closure of COM044. slightly ahead of schedule and under budget.

COM043 now has a go-live date of 14th May, with the UAT being completed successfully and signed off. There has been some overspend on this one and the PM will be preparing a PICCL to cover this shortly.

The delay to COM043 has meant that the milestones for COM045 have had to be pushed back, with delivery into Live now expected in early July. Resources and support have been secured. COM046 is continuing pretty much as planned, with the Live deployment due in mid-June. Again, resources are booked for this.

Finally, we have our intern starting soon and he will be able to get started on the JIRA upgrade in June.

 

 

RAG Status and Forward Look

Resources

 

 Section Two: Projects Not Started

Project Info     Project Manager's Commentary
COM047  Annual JIRA Upgrade
Scheduled to start in June 2019

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

COM036 BI - Business Objects Upgrade

Compliance

Milestones

Completed

RAG Status 

BLUE

Report by Chris Konczak for April 2019

Achievements in Last Period

Project closed: Closure Report

COM041 Decommission legacy Windows hosting

Compliance

 

Milestones

Close Closure complete 30-May-2019

 

RAG Status

AMBER

 Report  by Tim Gray for April 2019

Achievements in Last Period

  • Site migrations completed and signed off

Issues

  • Project closure milestone moved out due to lack of Project Manager availability 

Next steps

  • Complete project closure

 

COM043 SOA Upgrade to v12

Compliance

Milestones

Delivery 14-May-2019
Deployment Sign Off Review 30-May-2019
Close 14-June-2019

RAG Status

GREEN

Report by Adam Wadee for April 2019

 

Achievements in Last Period

  • UAT has been completed and we are now preparing for the live deployment on Tuesday 14th May.

Issues

  • No issues to report.

Next steps

  • Go Live on 14th May.

  • Sign off deployment.

  • Start closure tasks.

COM045 IDM Database Upgrade

Compliance

Milestones

DEV build sign off 08-May-2019
Integration testing sign off 28-May-2019
Acceptance testing sign off 17-Jun-2019
Deploy to LIVE 16-Jul-2019
Deployment Sign Off Review 31-Jul-2019
Project Closure 09-Aug-2019

RAG Status

AMBER (Resolved). Project delayed due to COM043 SOA upgrade experiencing infrastructure issues on all environments.

Report by Chris Konczak for April 2019

Achievements in Last Period

  • Project milestones and resourcing replaned after the delay due to COM043 SOA Upgrade.
  • Resourcing secured

Issues

  • TEST upgrade delayed due to COM043 issues with the environments (now resolved). Delivery milestone delayed from 08/05/2019 to 16/07/2019. COM043 deploying to LIVE on 14th May when the TEST environment will become available for COM045 to commence the upgrade.
  • Carryover of 2 days for unplanned effort into 2019/20 to complete the closure tasks.

Next Steps

  • Commence the TEST upgrade
  • Integration testing

COM046 - Annual WIKI upgrade

Compliance

Milestones

Milestones

Integration testing sign off 16-May-2019
Acceptance sign off 14-Jun-2019
Deploy to LIVE 26-Jun-2019
Deployment Sign Off Review (DSOR) 08-Jul-2019
Closure 29-Jul-2019

 

RAG Status

GREEN

 

Report by Chris Konczak for April 2019

Achievements in Last Period

  • Brief sign off by project team and WIS approval achieved
  • DEV upgrade completed, tested and signed off

 

Issues

  • None

 

Next Steps

  • Upgrade to TEST
  • Integration testing sign off

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

COM040 - JIRA Upgrade

Project closed - Closure Report

 

COM042 - GDPR Preparation for Applications  Project closed - Closure Report
COM044 - Serengeti Annual Upgrade Project closed - Closure Report
COM048 Bi-Annual CalSync Upgrade Project withdrawn - Decision
COM036 - BI Business Objects Upgrade Project closed - Closure Report

Section Five: Actions/Notes from monthly programme meeting 

Project Action / Notes Responsibility    Status
       
       
AttachmentSize
Image icon com-forwardlookapr19.jpg88.18 KB