Report for January 2020
- Report Date
- January 2020
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
COM043 - Previously reported issues now resolved. Awaiting agreement on dates for Go Live. Milestones to be updated
COM045 - Suspension renewed. Plans for deployment will depend on outcomes of COM043. To be monitored.
COM050 - Project just started. Planning stage underway; expected to be completed late February.
COM051 - Continuing to progress, more or less to plan. Need to address management of effort for Service Management in ASTA.
COM052 - Analysis & design work being carried out by project team. Build of new VMs being progressed.
COM055 - Migrations stalled because of issues with migration tool. Project has been escalated to SLT.
COM056 - Due to start early February; request submitted to WIS 07/02.
The proposed CalSync upgrade has been withdrawn from this year's COM programme, with the effort transferred to the TTU programme.
RAG Status and Forward Look
Resources
Section Two: Projects Not Started
COM054 | Annual JIRA Upgrade | tbc (Student Intern) | Starting June 20 |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||
COM043 SOA Upgrade to v12
Compliance Milestones
RAG Status AMBER |
Report by Adam Wadee for January 2020 Achievements
Issues
Next steps
|
||||||||||||||||
Compliance Milestones Suspended
RAG Status BLUE |
Report by Chris Konczak for January 2020 Suspension to be continued. Review date: 14/02/2020 |
||||||||||||||||
Compliance Milestones To be set in planning RAG Status GREEN |
Report by Chris Konczak for January 2020 Achievements this period
Issues
Next Steps
|
||||||||||||||||
COM051 Office 365 Security Hardening Compliance Milestones
RAG Status: GREEN
|
Report by Kevin Hone for January 2020 Achievements in Last Period:
Issues:
Next Steps:
|
||||||||||||||||
COM052 C-Host Infrastructure Replacement Compliance
Milestones
RAG Status GREEN
|
Report by Mark Downey for January 2020
Achievements in Last Period:
Issues
Next Steps
|
||||||||||||||||
COM055 O365 Staffmail Migration Compliance Milestones Pilot migration: 21-Jan-20 Migration batches: Feb - Jun 2020
RAG Status RED - project has stalled because of issues with migrations
|
Report by David Watters for January 2020 There is an on-going issue with the migration tool, and its ability to connect to the MicroSoft infrastructure. The issue is on the MS side and ISG teams are working with MS to resolve. This has further pushed back the pilot migration, which was already postponed due to strike action in December. We are against a deadline of July 2020 for de-commissioning of Staffmail. A full report for SLT is being prepared and will be circulated by end January. See this update here: https://secure.projects.ed.ac.uk/project/com055/status/4 |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
COM047 Annual JIRA Upgrade |
Project closed: closure report |
COM053 CalSync Bi Annual Upgrade | Project withdrawn: withdrawal |