Report for September 2021
- Report Date
- September 2021
Programme Status Report for COM Programme
Report compiled by David Watters (Programme Manager) for Alex Carter (Programme Sponsor)
Section 1: Programme Summary
Programme Manager's Commentary
The month of September has been mixed for the COM programme, with some progress being made on the continuing projects, some sticking points on others and a couple of new projects not being started as planned:
- COM045 is waiting to deploy the upgrade to Oracle 12 (in Live) now scheduled for early/mid October. There have been further discussions round the upgrade of the database to Oracle 19 before the EOL date for Oracle 12 (March 2022). This is expected to be done over the next few months.
- COM057 closed as expected and the project team - rightfully - received plaudits for a job well done on this one.
- COM059 is continuing with the build of the new Sharepoint solution and the reports coming back from the project team are all positive.
- COM055 is still waiting to be closed. This has been pushed back by a few weeks because of the PM's workload.
- COM061 has been progressing, with upgrades now applied in DEV and TEST. UAT is about to start and a go-live date for the upgrade has been arranged.
- COM062 has had problems with its planning and estimations. These have now been completed and submitted to Apps Review. Resources are booked and work is starting on the upgrade of DEV in early October.
- COM063 (Serengeti) has not been able to start because of the unavailability of resources in Project Services. We are looking at another way of running this project with Production Management taking a lead.
- COM064 (Business Objects) has also not been able to start because of the unavailability of resources in Project Services. It is believed that a PM will be available by the end of October.
Looking ahead, we are planning to deliver the IDM DB Upgrade and the JIRA Upgrade in October. The Programme is also hoping to resolve the issues round the start of the Serengeti and Business Objects upgrades. Another project due to start soon is the Accessibility Statements project. This will be discussed with the relevant stakeholders.
Programme Resource Position
Programme RAG Overview & Forward Look
Section 2: Projects Not Started
Project Info |
Programme Manager's Commentary |
COM065 - Accessibility - remediation | Due to start 04/10/2021 |
COM066 - Bi-Annual Grouper Upgrade | Due to start 08/11/2021 |
COM067 - Wiki: Annual Upgrade | Due to start 15/11/2021 |
COM068 - API Upgrade | Due to start 14/02/2022 |
COM069 = Committees’ Intranet: Update end of life components and tightening of security and compliance | Due to start 07/02/2022 |
Section 3: Projects in Progress
Projects | Project Manager's Commentary | ||||||||||||||||||||||||||||||
Compliance Milestones Milestones
RAG Status GREEN |
Report by Chris Konczak for September 2021 Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
Compliance Milestones
RAG Status GREEN |
Report by Tim Gray for September 2021 Achievements this month
Issues
Next Steps
RAG Commentary
|
||||||||||||||||||||||||||||||
Compliance Milestones
RAG Status GREEN |
Report by Colin Watt for September 2021 Achievements this period
Issues
Next Steps
RAG Commentary
|
||||||||||||||||||||||||||||||
Compliance Milestones
RAG Status GREEN
|
Report by David Watters for September 2021 Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
Qlik-Sense and Qlikview Annual Upgrade Compliance Milestones
RAG Status Green |
Report by Chris Konczak for September 2021 Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
Compliance RAG Status RED |
Report by David Watters for September 2021 Project was due to start in Sep/Oct, but due to additional resource being provided to P&M, we do not have capacity within Project Services to start the project as planned. The delay in starting the project may impact Apps overall plan for 21/22 resulting in key projects not being delivered." |
||||||||||||||||||||||||||||||
Annual Business Objects Upgrade Compliance RAG Status RED |
Report by David Watters for September 2021 Project was due to start in Sep/Oct, but due to additional resource being provided to P&M, we do not have capacity within Project Services to start the project as planned. The delay in starting the project may impact Apps overall plan for 21/22 resulting in key projects not being delivered." |