Report for February 2022
- Report Date
- February 2022
Programme Status Report for COM Programme
Report compiled by David Watters (Programme Manager) for Alex Carter (Programme Sponsor)
Section 1: Programme Summary
Programme Manager's Commentary
The month of February has been another busy one for the COM programme, with some progress being made on the continuing projects, some planning on recently initiated projects but there are still delays with some projects:
- COM045 is now ready to close with the deployment being signed off after further testing. This has seen more effort being used and the change control for the budget adjustment and the closure report are anticipated in the next week or so.
- COM059 is continuing with the build of the new Sharepoint solution. There have been changes to the project budget and milestones and the latter are still being worked on. The programme and porfolio managers need to establish the 'spin-off' project covering the IDM Actions.
- COM061 has been suspended again, until late March, because a date for the LIVE deployment cannot be agreed with business users.
- COM063 has been delayed because of discussions with the vendor still taking place but these have now been resolved and the planning stage can go ahead.
- COM064 is continuing as planned, with the DEV environment successfully upgraded and lots of good work being carried on communications, training material and user familiarisation. The upgrade in TEST is due to go ahead in early March.
- COM065 is progressing as planned with the brief signed off and the project team starting on the required tasks.
- COM066 is causing a bit of concern because of the delays to planning (largely because of strike action). The scope and estimations are still ambiguous and so the projected has been reported as Red this month.
- COM067 is also progressing as planned with the brief now signed off and the project team starting on the upgrades.
- COM069 has been initiated and work on the project brief is under way - due mid-February
COM068 (API Upgrade) is earmarked to start this month, though we have been advised to assess the feasability of it being completed in 21/22
Programme Resource Position
Programme RAG Overview & Forward Look
Section 2: Projects Not Started
Project Info |
Programme Manager's Commentary |
COM068 - API Upgrade | Due to start 14/02/2022 |
Section 3: Projects in Progress
Projects | Project Manager's Commentary | ||||||||||||||||||||||||||||||||||||||
Compliance Milestones Milestones
RAG Status AMBER |
Report by Chris Konczak for February 2022Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||
Compliance Milestones Reviewed due to re-prioritisation based on SW Dev resource availability. Proposed new milestones:
RAG Status AMBER |
Report by Colin Watt for February 2022Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||
Compliance Milestones
RAG Status: BLUE (Suspended)
|
Report by David Watters for February 2022Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||
Compliance Milestones
RAG Status AMBER |
Report by David Watters for February 2022Achievements
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||
Annual Business Objects Upgrade Compliance Milestones
RAG Status AMBER |
Report by David Watters for February 2022Achievements
Issues
Next Steps
RAG Commentary:The current status is Amber because, although progress is being made in line with the project plan, there are two risks that could impact the deployment into Live. One is the impact of recent industrial action, and the other is the recent demands from P&M/Finance that the project team delay going live as it may cause problems for them. This has been addressed and mitigated but things can change.
|
||||||||||||||||||||||||||||||||||||||
Milestones (Note that these milestones are indicative and will be formalised once Project Brief approved)
RAG Status GREEN |
Report by Ailsa Glass for February 2022Achievements this period
Issues
Next Steps
This project is reporting GREEN as project activities are on track. However, there has been a missed milestone (Planning due 17/02/22). This is largely due to industrial action and availability of resource. A Change Request will be submitted to Apps Review with a revised date in due course. It is not envisaged that this delay will adversely impact the project. |
||||||||||||||||||||||||||||||||||||||
COM066 Milestones (All dates are indicative at this stage)
RAG Status AMBER |
Report by Stephen Stanley for February 2022Achievements in last period
Issues
Next Steps
RAG Commentary Description: Technical requirements yet to be confirmed. Key resource availability is compromised by potential impact of commitment to other projects of the same or higher priority. Impact: This puts the estimated delivery dates for 21/22 at risk. But current planned activity can continue without intervention. Plan: PM to work with technical team, when available, to agree plan and resource. |
||||||||||||||||||||||||||||||||||||||
COM067 Milestones
RAG Status GREEN |
Report by Chris Konczak for February 2022Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||
Committees’ Intranet: Update end of life components and tightening of security and compliance
Milestones (Note that these milestones are indicative and will be formalised once Project Brief approved)
RAG Status GREEN |
Report by Ailsa Glass for February 2022Achievements this period
Issues
Next Steps
This project is reporting GREEN as project activities are on track. However, the recent Industrial Action has contributed to difficulties securing stakeholders which may delay completion of the Planning milestone. Given that this project is not due to compete until the next financial year, it is not envisaged that this delay will adversely impact the project. |
Section 4: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary |
Closed on 15/09/2021 |
|
Closed on 04/11/21 |
|
Closed on 25/02/22 |