Programme Report for September 2012

Report Date
September 2012

 

Report compiled by Maurice Franceschi (IS Apps Programme Manager) for Mark Wetton and Anne-Marie Scott (Programme Owners)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

 

Section One: Programme Commentary, RAG and Resources Update

 

The DEI004 closed this month, and the Data Hub Enhancements project was transferred to TEL programme.

The DEI007 project delivers in October.

Once the balance row is reduced, programme will be almost balanced.

The approach now is to wait until the turn of the year and re-assess the business drivers for the planned projects before application for DEI funds.

At preset the Moodle Upgrade is likely to be still desirable to undertake, the Moodle Enhancements and the Social Hub projctes are not.

 

Actions from programme meeting

 

 

 

 Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary

AP12-042

Moodle Enhancements Funded

Milestones

Feb-13   Planning

Jun-13   Delivery  

RAG Status Green  

Plan Programme Owners agree with schedule.

However, TEL team will start the thinking in Q4 2012 to anticipate the issues and risks before project starts in 2013.

Proposal and Estimates

 

Dependencies Moodle Upgrade AP12-043

AP12-043

Moodle Upgrade Funded

Milestones

Jan-13   Planning

May-13   Delivery  

RAG Status Green

Plan Programme Owners agree with schedule.

However, TEL team will start the thinking in Q4 2012 to anticipate the issues and risks before project starts in 2013.

Proposal and Estimates

 

 

Dependencies Moodle Enhancements AP12-042

AP12-044

Social Hub Enhancements Funded

Milestones

Nov-12   Planning

Mar-13   Delivery  

RAG Status Green

Plan Programme Owners agree with schedule.

However, TEL team will start the thinking in Q4 2012 to anticipate the issues and risks before project starts in 2013.

Proposal and Estimates

 

Dependencies none

  
  

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

DEI006 (AP Number)

Card Servies for ODL Student

Funding

Milestones (Phase 2)  

Target dateTitle
14-Aug-2012DSOR : Phase 1 DSOR milestone achieved
17-Sep-2012Deployment - CANCELLED
17-Sep-2012Integration - Phase 2 - CANCELLED
17-Sep-2012Accceptance Phase 2 - CANCELLED
10-Oct-2012Phase 2 Build - Complete Peer Test
16-Oct-2012Closure

RAG Status

RED - over budget and to be closed after peer testing.

Report by Donna Cruickshank for September 2012

Achievements in Last Period

The Showstopper issue of last month (file transfer issues) was successfully resolved

the project was brought to a position where the build was complete and ready to be re-peer tested.

Issues

Following a meeting on 13 Sept with Bryan MacGregor and Maurice Franceschi, it was decided to stop the project because it was clear additional budget would be required to progress with integration testing, UAT, deployment etc - a breakdown of the remaining estimated effort was sent to Bryan.

Next Steps

In agreement with Bryan MacGregor, one day of effort (maximum) is to be spent to complete peer testing and  close the project. This will mean that the project should close having used 125 days (out of an approved budget of 125 days).

DEI007 ( AP Number)

Distance Education Data Hub Design Funded

Milestones  

Target dateTitle
24-Oct-2012BRD sign off
01-Nov-2012Closure
 

RAG Status

GREEN

Report by Franck Bergeret for September 2012

 

Achievements in Last Period 
  • BRD review meeting held with stakeholders 24/9.
  • 2nd deliverable: High Level Architecture document de-scoped from this project. Will be picked up as part of next project AP12-045 Data Hub Enhancements.

 

Issues 
  • N/A 
Next Steps
  • Further work required for BRD final sign off: delayed BRD sign off to 24/10 (was 25/9).
  • Then move to closing project.

 

 
  

 

Section Four: Projects Closed / Withdrawn

 

Project InfoProject Managers Commentary

DEI008 (AP Number)

Distance Education Social Hub Funded

Report by Franck Bergeret for August 2012

This project was closed on 13th Aug 2012

Please see the completion report for further information

DEI004 (AP12-917)

ODL in the Student record Phase 2

Funded

Report by Franck Bergeret for September 2012

This project was closed on 7th Sept 2012

Please see the completion report for further information

 

 

Actions from September Programme Meeting (5th October)

DEI007 to be closed in OCtoberDave 
Need clarification on whether Personal Tutors will pick up DEI006 developmentsMaurice 
Dave will no longer act as Senior Supplier for DEI programme (but wil be SS for Data Hub Enhancements project)Dave to inform WIS 
Move the three not started DEI projects to TEL, close DEI programmeMaurice 
   

 

Actions from August Programme Meeting (13th Sept)

DEI007 : Descope High Level Architecture doc from project and closeFranckDone
DEI006 : Stop further work, close project Bryan to speak to ShielaDonna BryanDone
Move Data Hub out of TEL Byran to confirm with Simon Either transfer if the days are available, into TEL Withdraw if funding is not confirmed

Bryan

Maurice

Done
No projects to start until 2013. We leave as planned in ASTA, but funding must be confirmed before we start any project.MauriceDone