Report for October 2019
- Report Date
- October 2019
Workflows options appraisal complete and signed off. Project will now be closed.
Collections as data report complete. Project will now be closed.
Now planning next tranche of projects for the programme, in particular Digital Scholarship Tools and Collections as Data proof of concept.
Resourcing challenges within the programme this month due to sickness in the team. Discussing with Kirsty and Mark Ritchie how best to cover resource gaps.
Project Info | Project Managers Commentary | ||||||||||||
DLIB001 Digitised Library Workflows Options Appraisal Project Overview Milestones
RAG Status GREEN |
Report by Sue Woodger for October 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||
DLIB002 Collections as Data Milestones
RAG Status GREEN |
Report by Stephen Roy October 2019 Achievements in Last Period
Issues
Next Steps
|