Report for October 2019

Report Date
October 2019

Workflows options appraisal complete and signed off. Project will now be closed.

Collections as data report complete. Project will now be closed.

Now planning next tranche of projects for the programme, in particular Digital Scholarship Tools and Collections as Data proof of concept.

Resourcing challenges within the programme this month due to sickness in the team. Discussing with Kirsty and Mark Ritchie how best to cover resource gaps.

Project Info Project Managers Commentary

DLIB001

Digitised Library Workflows Options Appraisal Project Overview

Milestones

Close    

31-Oct -2019

 

 

RAG Status

GREEN

Report by Sue Woodger for October 2019

Achievements in Last Period

  • Final report was signed off by project team in October
  • Project sponsor took the report to the programme board and they approved it on 25 October 19
  • Closure report has been submitted to team members for signoff

Issues

  • No issues this month

Next Steps

  • Closure report to be signed off and project closed

 

 

 

DLIB002

Collections as Data

Milestones

Plan Planning 01-Feb-2019
Analyse Analysis Output 31-Jul-2019
Deliver Delivery Review 01-Aug-2019
Close Closure 09-Aug-2019

 

RAG Status

GREEN

Report by Stephen Roy October 2019

Achievements in Last Period

  • Project is awaiting closure

Issues

  • None

Next Steps

  • Close project
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
Yes
Escalated to
Mark Ritchie, Head of Project Services
RAG Commentary
Programme has resource challenges