Report for November 2019

Report Date
November 2019

Programme is going through a period of assessment within Libraries after the deliver of major analysis pieces of work.

There have been resource challenges with absence of key staff and competing demands within Libraries. Resource challenges escalated within Project Services and IS and resolution is imminent.

Plan to pick up target operating model work in January.

Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
Yes
Escalated to
Mark Ritchie, Head of Project Services
RAG Commentary
Resource challenges within Project Services and competing work challenges in Libraries.