Report for January 2019
- Report Date
- January 2019
Report compiled by Hilary Shand
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
This programme is currently compiled of 2 projects DLIB001 & DLIB002. Both projects are pieces of Business Analysis work.
DLIB001 - Digitised Library Workflows Options Appraisal
Progress has been made in getting a brief signed off and a project kick off meeting to discuss tasks
DLIB002 - Collections as Data
Project brief now complete and due for submission to WIS on 08.02.19
Project name has been changed from Digital Datsets
RAG Status
The programme status is currently GREEN. Both projects are progressing.
Resource Update
Data | ||||||
Project Status | Name | Budget 18/19 | This month | This year | Total to Date | To Complete This Year |
In Progress | DLIB Digital Library Programme 18/19 | 7 | 23 | 23 | 55 | |
DLIBPB2 18/19 Digital Library Programme Balance Row – Sponsor Funded | 0 | 0 | 0 | 0 | 0 | |
DLIB001 Digitised Library Workflow Options Appraisal | 2 | 4 | 4 | 46 | ||
DLIB002 Collections as Data | 2 | 2 | 2 | 46 | ||
In Progress Total | 0 | 12 | 29 | 29 | 147 | |
Grand Total | 0 | 12 | 29 | 29 | 147 |
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | |||||||||||||||
DLIB001 Digitised Library Workflows Options Appraisal Project Overview Milestones
RAG Status GREEN |
Report by Sue Woodger for January 2019 Achievements in Last Period
Issues
Next Steps
RAG commentary: N/A
|
|||||||||||||||
DLIB002 Collections as Data Milestones
RAG Status
|
Report by Hilary Shand for January 2019 Achievements
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
|
|
|