Report for August 2020
- Report Date
- August 2020
Report compiled by Karen Stirling, DLIB Programme Manager for Kirsty Lingstadt (Programme Owner), Stephen Roy, Adam Wadee
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The Programme Commentary
The programme is
- DLIB003 Language Online - Dual Language for Collections - Data migrated to test environment and testing completed, planning live migration activity
- DLIB004 Digital Workflows - Goobi Implementation - The work on configuring the workflows has proved to be more complex and time consuming than expected. This was compounded by the supplier having reduced resources available due to staff vacation then subsequent COVID-19 Quarantine. Project delivery dates have been revised.
- DLIB005 Procurement for DAMS (Digital Asset Management System) - the key items which are now impacting project and RAG status from Programme board update are:
-
Current procurement officer is likely to be deployed to People & Money project, and the procurement team have indicated that due to internal resource constraints they lack the available resource to replace him
-
Final procurement route decision has yet to be finalised. The project brief cannot be submitted to WS until this decision has been made, and therefore the planning milestone is likely to be delayed
-
- DLIB006 Library Databases and Licensed Content - User Discovery and Access Analysis - project planning and brief were approved and now ready to commence analysis on return of Business Lead from annual leave.
Due to the impact of Coronavirus, SLT review of project priorities has resulted in a stronger focus on this programme of work. As such Programme Owner has submitted blue paper to ISG SLT for additional funding for FY20/21 and extra funding for FY21/22. Funding increase has still to be confirmed.
Overall Programme RAG: GREEN
Forward Look and RAG
Resource Position
Section Two: Projects Not Started for 19/20
Project Info | Project Manager's Commentary |
DLIB007 Access to All Online Collections | PM/BA to be requested for project expected to commence in this financial year |
Section Three: Projects in Progress
Projects | Project Manager's Commentary | ||||||||||||||
DLIB003 Language Online - Dual Language for Collections Sponsor Funded / Discretionary
RAG Status : GREEN
|
Report by Alex Ross for August 2020 Achievements in Last Period
Issues
Next Steps
The status of this project is GREEN. |
||||||||||||||
DLIB004 Digital Workflows - Goobi Implementation Sponsor Funded / Discretionary
RAG Status : GREEN
|
Report by Frankie Quinn for August 2020 Achievements for this Period
Issues
Next steps
The project current status is GREEN
|
||||||||||||||
DLIB005 Procurement of Digital Asset Management System (DAMS) Sponsor Funded / Discretionary
RAG Status: RED
|
Report by Alex Ross for August 2020 Achievements in Last Period
Issues
Next Steps
The current status of this project is RED due to current procurement officer likely being deployed to People & Money project, while the procurement team are still establishing suitable replacement resource. This represents a significant risk to the project as until a suitable replacement procurement manager can be assigned, the project brief cannot be signed off, meaning project progress will be stalled and the ability of the project to be delivered on time will be impacted. This would have a significant impact on the overall Digital library Programme and also delivering digital content to students, researchers and staff. This issue has been escalated to the project sponsor who will work to ensure that an appropriate replacement procurement resource can be secured
|
||||||||||||||
DLIB006 Library Databases and Licensed Content - User Discovery and Access Analysis Sponsor Funded / Discretionary Milestones
RAG Status : GREEN
|
Report by Sue Woodger for August 2020 Achievements in last period
Issues
Next Steps
The project current status is GREEN
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
|
|
Attachment | Size |
---|---|
dlib_forward_look_aug_20_v1.png | 66.83 KB |
dlib_resource_aug_20_v.1.png | 52.73 KB |