Report for Jan 2019
- Report Date
- January 2019
Report compiled by Programme Manager for Programme Owner
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Majority of the programme progress has been on project DTI026.
- DTI018 (Continuous Service Improvement APIs) -
- DTI026 (API Gateway and API Management Tool) -
- DTI028 (Infrastructure) -
- DTI029 9Maturing the Service) -
RAG Status and Forward Look
Overall, the programme is AMBER at this time as although new milestones have been agreed for DTI026 & DTI028, the other 2 projects has still being reviewed. Additionally new issues have been raised this month.
Resource Summary
Section Two: Projects Not Started
There are no projects not started.
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||
DTI026 API Gateway and API Management Tool
Milestones
RAG GREEN |
Report for January 2019
Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||
DTI028 Maturing the API Infrastructure Milestones
RAG AMBER |
Report for January 2019
Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||
DTI029 Maturing the API Service New Proposed Milestones To Be Confirmed RAG AMBER |
Report for December 2018 Achievements in Last Period
IssuesNo new issues Next Steps
|
||||||||||||||||
DTI018 Continuous Service Improvement APIs New Proposed Milestones To Be Confirmed RAG AMBER
|
Report for December 2018 Achievements in Last Period
Deep dive analysis of the current API demand has now been completed. This now gives the Sponsoring Group clearly visibility of the demand in order to prioritise. Initial recommendations were discussed with Sponsoring Group and reprioritisation logic agreed at a meeting on 28.11.18. However further progress on this project has been difficult to achieve this month due to other demands on Service Leads time. As a result the new project milestones have not been determined. Work on UAT approach has not progressed due to A/L on the delivery team. Issues
Next Steps
|
Section Four: Closed, Suspended or Withdrawn Projects
Project Info | Project Manager's Commentary |
---|---|
DTI013 Analysis and Specification of Requirements | Project closure approved by WIS 2/2/18 |
DTI014 Enterprise API Technology | Project closure approved by WIS 17/11/17 |
DTI015 Student Record APIs | Project closure approved by WIS 1/9/17 |
DTI016 UCP Pilot API |
22/12/17 - Project withdrawal approved by WIS 22/12/17 - PICCL Change 6 6/12/17 - Recommendation is to withdraw and review requirements again in 18/19 due to PICCL Issue 5, project risk 5 13/10/17 - Project suspension approved by WIS 13/10/17 - PICCL Change 4 |
DTI017 VLE API |
Project closure approved by WIS 23/3/18 5/2/18 - Recommendation is to close project early - PICCL Decision 8 6/12/17 - Recommendation is to review conditions for removing project from suspension in 18/19, PICCL Change 7, project risk 10, project risk 11 17/11/17 - Project suspension approved by WIS 17/11/17 - PICCL Change 7 |
DTI023 Analysis and Requirements | Project withdrawal approved by WIS 15/12/17 - PICCL Change 1 |
DTI024 Maturing Student Record APIs | Project closure submitted to WIS 29/6/18 |
DTI025 Approved Small APIs | Project withdrawal approved by WIS 13/10/17 - PICCL Change 1 |
COM027 Enterprise API Foundation | Project closure approved by WIS 9/6/17 |
Section Five: Actions/Notes from monthly meeting :