Programme Commentary
Assessment has been ongoing in consideration of hosting the WS02 gateway and management tool in the cloud. This has resulted in slowing pace of delivery of other programme activities such as the Target Operating Model and Stakeholder Engagement. Now that a decision has been reached to support the could solution,the programme can be re-planned for the remainder of the year.
- DTI018 (Continuous Service Improvement APIs) - work is now progressing on the UniDesk API
- DTI026 (API Gateway and API Management Tool) - handover activities are continuing in anticipation of a delivery team members departure from post
- DTI028 (Infrastructure) - work is ongoing on the Python templates
- DTI029 (Maturing the Service) - minimal progress. Currently being reviewed.
Programme Status is currently Red. There has been various changes to effort and timelines across DTI026 & DTI028/029. As a result 3 projects are now status Red and one is Amber (DTI018). A deep dive into programme budget is underway, however, initial assessment shows a potential overspend to date of 7k.
Resource Summary
Effort is currently being confirmed for several work packages, also delivery dates have moved based on resource bookings. Therefore resourcing will need to be assessed in depth as some days of effort will move into next financial year and other effort will be realigned with remaining deliverables.
Portfolio | (All) | |||||
Programme | Digital Transformation - Enterprise APIs (API) | |||||
Category | (All) | |||||
Data | ||||||
Project Status | Name | Budget 18/19 | This month | This year | Total to Date | To Complete This Year |
In Progress | DTI018 Continuous Service Improvement | 100 | 12 | 71 | 294 | 30 |
DTI028 Maturing the API Infrastructure | 13 | 79 | 125 | 51 | ||
DTI029 Maturing the API Service | 100 | 2 | 39 | 116 | 24 | |
DTI026 API Gateway and API Management Tool | 26 | 145 | 254 | 35 | ||
DTIP03 18/19 Enterprise APIs Programme Mgmt | 89 | 17 | 209 | 209 | 15 | |
In Progress Total | 289 | 69 | 543 | 998 | 154 | |
Grand Total | 289 | 69 | 543 | 998 | 154 |
Section Two: Projects Not Started
There are no projects not started.
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||
DTI026 API Gateway and API Management Tool
Milestones
RAG RED |
Report for April 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||
DTI028 Maturing the API Infrastructure Milestones
RAG: RED
|
Report for April 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||
DTI029 Maturing the API Service Revised Milestones To Be Confirmed RAG: AMBER
|
Report for April 2019 Achievements in Last Period
IssuesNo New issues Next Steps
|
||||||||||||||||
DTI018 Continuous Service Improvement APIs
RAG RED
|
Report for April 2019 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed, Suspended or Withdrawn Projects
Project Info | Project Manager's Commentary |
---|---|
DTI013 Analysis and Specification of Requirements | Project closure approved by WIS 2/2/18 |
DTI014 Enterprise API Technology | Project closure approved by WIS 17/11/17 |
DTI015 Student Record APIs | Project closure approved by WIS 1/9/17 |
DTI016 UCP Pilot API |
22/12/17 - Project withdrawal approved by WIS 22/12/17 - PICCL Change 6 6/12/17 - Recommendation is to withdraw and review requirements again in 18/19 due to PICCL Issue 5, project risk 5 13/10/17 - Project suspension approved by WIS 13/10/17 - PICCL Change 4 |
DTI017 VLE API |
Project closure approved by WIS 23/3/18 5/2/18 - Recommendation is to close project early - PICCL Decision 8 6/12/17 - Recommendation is to review conditions for removing project from suspension in 18/19, PICCL Change 7, project risk 10, project risk 11 17/11/17 - Project suspension approved by WIS 17/11/17 - PICCL Change 7 |
DTI023 Analysis and Requirements | Project withdrawal approved by WIS 15/12/17 - PICCL Change 1 |
DTI024 Maturing Student Record APIs | Project closure submitted to WIS 29/6/18 |
DTI025 Approved Small APIs | Project withdrawal approved by WIS 13/10/17 - PICCL Change 1 |
COM027 Enterprise API Foundation | Project closure approved by WIS 9/6/17 |
Section Five: Actions/Notes from monthly meeting :
Attachment | Size |
---|---|
api_resources.jpg | 56.46 KB |