Report for January 2020
- Report Date
- January 2020
The API programme has come to an important point where we have delivered a lot of the major infrastructure and basic service elements.
We now need to review where we are and plan where we are going both in terms of vision and in terms of further projects in the near future to fully develop the service and move to an API First culture.
There is a planning workshop on 13th February to move this forward.
DTI018 (Continuous Service Improvement APIs) - Pure API and EDW Person API delivered to WS02. UniDesk API undergoing internal testing.
DTI026 (API Gateway and API Management Tool) - Cloud WSO2 configured. Handover to Production to be agreed prior to closure.
DTI028 (Infrastructure) - Review workshops completed. Project set for closure.
DTI029 (Maturing the service) - Project approved for closure but scope to be reviewed following planning workshop on 13th Feb.
Programme status is Amber as there have been delivery challenges.
Section Two: Projects Not Started
There are no projects not started.
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||
DTI018
Milestones
RAG: AMBER
|
Report for January 2020 Achievements in Last Period
Issues
Next Steps
|
||||||||
DTI026 API Gateway and API Management Tool
Milestones
RAG: AMBER |
Report for January 2020 Achievements in Last Period
IssuesNext Steps
|
||||||||
DTI028 Maturing the API Infrastructure Milestones
RAG: AMBER
|
Report for January 2020 Achievements in Last Period
Issues
Next Steps
|
||||||||
DTI029 Maturing the API Service Revised Milestones To Be Confirmed Post Workshop. RAG: AMBER
|
Report for January 2020 Achievements in Last Period
Issues
Next Steps
|