We are working towards the conclusion of this phase of the API programme, aiming to launch the initial API service.
There are some development and testing tasks that are nearing completion that have had issues to resolve in order to complete.
Service management and development are collaborating on completion of the initial service delivery model for APIs. This has taken longer than anticipated because of resource pressures within Service Management and Development but is making steady progress.
If resource pressures in Service Management and Development could be eased then this work could complete more quickly.
We are in early stages of a re-planning exercise to clarify the longer term vision for API's at the University.
Completion of regression testing within WSO2 and signed off.
Unidesk API
Liaise with Service Team regarding progression through internal Test and prep prior to external testing.
Tester still unable to receive response. Ticket returned to
Software Dev corrected outstanding issues with API and re-released for test.
Person ID resolver API for EDW
Testing raised issue with incomplete responses. Investigation ongoing.
Issues
With UniDesk upgrade on the horizon should we continue to develop the present API. It was confirmed that the API being developed at present would remain in use during the staggered upgrade and was therefore worth continuing with.
Next Steps
PURE Resolver Id API
Complete deployment checklist
Creation and sign off of authentication SharePoint site for locker process .
Authentication process added to Production Wiki page.
Unidesk API
Liaise with Service Team regarding progression through internal Test and prep prior to external testing.
Sign off of internal testing of API via WSO2.
Initiation of external testing. St Andrews lined up as test external institution.
Promotion of API from Test to Live.
Person ID resolver API for EDW
Correction of error and re-release for test.
Completion of testing within WSO2 and signed off.
Handover process for API's to be agreed. Liaise with Service and Production Management regarding support and handover process.
Update project report in step with agreed closure process.
Closure report released for initial review.
Issues
At this point in time it is not clear roles and responsibilities regarding ongoing support. It has been agreed this should be picked up by DTI029 Maturing the API Service allowing this project to progress to closure.
Service Management and Development Services continue to build on initial service delivery model.
Weekly review meetings continuing to revive project momentum.
Development Services reviewing and updating initial framework documentation as a result of project evolution.
Issues
Present plan is for Service Management and Development Services to develop the initial service delivery model. Service management and development have little spare capacity to devote to this exercise and it is therefore taking longer than expected to complete. Once this is completed the scope of remaining tasks and responsibility for them will become clear.
It has been proposed that the scope of this project should be increased to include the merge of IS instance of WSO2 with that of People and Money. This needs to be formally agreed before being raised as revised scope.
Next Steps
Publishing process to be agreed and then raised with People and Money.
Service "Walk Through" scheduled with Production Management and Enterprise Architecture.
Service Management and Development Services to complete development of initial service delivery model.
Clarify tasks and those responsible to complete tasks to deliver initial service model and re-plan project accordingly.
Revised service to be raised with Project Services PMO.
Commence review of Communications tasks to publicise the API service.