Report for September 2018
- Report Date
- September 2018
Report compiled by Daniel Emerson (Programme Manager) for Alex Carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
REPORT for SEPTEMBER
Key Achievements in Last Period
- Completed DT budget review – no change to BI Tools budget.
- Resolved scope for Qlik Implementation (DTI 034)
- Delineating to provide time to ensure a strategic approach is taken whilst allowing the ongoing installation of Qlik products.
- Resolved scope for BI Framework (DTI 046)
- Focusing the strategy element just on the reporting tools. Wider BI strategy to be taken forward by Lynda Hutchison.
Top Issues
- Establish a clear scope for project: Developing the BI Community (DTI 031) and decide how best to proceed.
Key Next Steps
- End of planning submission: Qlik Implementation (DTI 034)
- Estimate and initiate new project to pick up descoped items from DTI 034
- Consider BI Tools data security (authorisation) integration with EDW, potential candidate for inclusion in new project.
- Re-assess and re-prioritise the programme projects against remaining time and budget
- Work with other programmes to lay out the vision for BI/MI capability going forward.
- End of planning submission: BI Framework (DTI 046)
Overall the programme is rated at AMBER.
There are some delays in projects, and uncertainties around scope of the Community project (DTI 031) which has no allocated budget this year, flagged as RED. There are also uncertainties around the effort involved in setting up Qlik products (particularly authorisation security) and consolidating/migrating the existing QlikView applications in use. It is possible this could require significantly more work than originally estimated, and raises an Amber risk that we cannot meet all the original programme deliverables within budget.
Status and Forward Look
Resource Summary
Note: Budget for 18/19 not showing, will seek assistance to correct.
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
DTI047 Embed & Optimise | Initiated. Planned Start Jan-19 | |
DTI048 BI Search Space | Planned Start Apr-19 |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
DTI031 - Develop the BI Community
Discretionary Milestones 02-Feb-2018 Exit Planning 14-Jul-2018 Project Delivery 28-Jul-2018 Project Closure |
This project was previously considered for withdrawal (at BIT board meeting 23/05) due to difficulty defining and measuring clear deliverables. Received a proposal for developing a BI community from service management. The proposal will inform whether it makes sense to continue the activity as a re-defined project, or incorporate it into BAU activities.
Achievements this period
Issues
Next Steps
RAG - RED The project is reporting a status of red, being over two months past the expected closure date and with uncertainty around the scope going forward. |
|
|
DTI 034 - Qlik Implementation
Discretionary Milestones 13/08/2018 Start 30-Sep-2018 Planning 15-Jan-2019 Delivery 15-Feb-2019 Project Closure
|
Project is now in the planning stage Achievements this period
Issues
Next Steps
RAG - Amber Time and Scope are listed as Amber, due to uncertainty on the project scope and the delay this has caused in the drafting of the Project Brief |
DTI046 - BI Framework Discretionary Milestones TBC
RAG Green |
Report by Geoff Cropley for August 2018 Achievements this periodProject planning and project brief has been completed and awaiting key stakeholder identification and engagement. Project charter and Strategy workshop inputs have been completed together with the Communications plan. IssuesNone. Next StepsIdentification of business key business stakeholders to complete the project team. Submission of project brief through project governance.
RAG - Green
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary | |
---|---|---|