Report for November 2018
- Report Date
- November 2018
Report compiled by Daniel Emerson (Programme Manager) for Alex Carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
REPORT for NOVEMBER
Key Achievements in Last Period
- Continued work to define the ongoing BI/MI programme going forward, and giving a clearer focus to this programme within that.
- End of planning achieved: Qlik Implementation (DTI034).
- End of planning achieved: BI Framework (DTI046).
- Withdrawn ‘Developing the BI Community’ (DTI031).
Top Issues
Key Next Steps
- Write the programme brief for ongoing BI/MI activity.
- Progress DTI034 and DTI046
Overall the programme is rated at GREEN.
Status and Forward Look
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
DTI047 Embed & Optimise | Initiated. Planned Start Jan-19 | |
DTI048 BI Search Space | Planned Start Apr-19 |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
|||||||||||||||
|
||||||||||||||||
|
||||||||||||||||
DTI 034 - Qlik Implementation
Discretionary Milestones 13/08/2018 Start 23-Nov-2018 Planning 06-Mar-2019 Delivery 29-Mar-2019 Project Closure
|
Achievements this period
Issues
Next Steps
RAG - Green End of Planning delayed due to unavailability of previous Project Manager and change of Project Manager |
|||||||||||||||
DTI046 - BI Framework Discretionary Milestones
RAG Green |
Report by Geoff Cropley for November 2018
Achievements this period Project end of planning has completed. A review of the scope and deliverables was completed and agreed with the key stakeholders and a PICCL was produced to reflect the revised scope and timetable. Issues None. Next Steps Develop the Technical Strategy for the BI Tools Service. RAG - Green |
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary | |
---|---|---|
DTI031 - Develop the BI Community | Withdrawn - will be met with an appropriate comms plan, a means of raising and responding to queries as outlined by Service Management for ongoing BAU, and regular sessions for key users to input into the ongoing development and maturing of our BI capability. | |
Attachment | Size |
---|---|
bit_forward_plan_2018-11.png | 33.19 KB |
bit_effort_data_2018-11.png | 23.56 KB |