Report for February 2019
- Report Date
- February 2019
Report compiled by Daniel Emerson (Programme Manager)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
REPORT for February 2019
Key Achievements in Last Period
- Progressing Qlik Implementation (DTI034).
- Progressing BI Framework (DTI046).
- Continuing to define ongoing BI Programme.
- Begun addressing EDW accessibility issue.
Top Issues
- Accessibility of EDW for reporting, no agreed mechanism in place.
- Unresolved EDW issues, Service Management gaps, and unknown legacy QlikView migration effort require scoping and re-prioritisation of programme deliverables.
Key Next Steps
- Progress DTI034
- Progress DTI046
- Change scope and timing for DTI047
Overall the programme is rated at AMBER.
Status and Forward Look
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
DTI047 Embed & Optimise | Initiated. Planned Start Jan-19 | |
DTI048 BI Search Space | Planned Start Apr-19 |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
|||||||||||||||
|
||||||||||||||||
|
||||||||||||||||
DTI 034 - Qlik Implementation
Discretionary Milestones 13/08/2018 Start 23-Nov-2018 Planning 06-Mar-2019 Delivery 29-Mar-2019 Project Closure
|
Achievements this period
Issues
Next Steps
RAG - Amber Project delays due to resource constraints |
|||||||||||||||
DTI046 - BI Framework Discretionary Milestones
RAG Green |
Report by Geoff Cropley for February 2019
Achievements this period The development of the Technical Strategy has been completed. Design for Pilot reporting is underway. Issues None. Next Steps Commence pilot reporting. Complete the the delivery of the communication plan. RAG - Green |
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary | |
---|---|---|
DTI031 - Develop the BI Community | Withdrawn - will be met with an appropriate comms plan, a means of raising and responding to queries as outlined by Service Management for ongoing BAU, and regular sessions for key users to input into the ongoing development and maturing of our BI capability. | |
Attachment | Size |
---|---|
bit_forward_plan_2019-02.png | 33.72 KB |
bit_effort_data_2019-02.png | 30.99 KB |