Report for May 2019

Report Date
May 2019

Report compiled by  Geoff Cropley (Programme Manager)

Section One: Programme Commentary, RAG and Resources Update

Programme Commentary

REPORT for May 2019

Key Achievements in Last Period

  • Qlik migration process completed (DTI034).
  • BI Tools Framework (DTI046) complete.
  • Re-prioritisation of programme deliverables for DTI047 complete.
  • EDW connectivity options still under investigation.
  • Agreed programme sponsor for ongoing BI Programme.
  • New Programme manager appointed 

Top Issues

  • Accessibility of EDW for reporting, no agreed process in place for desktop clients (affecting QlikView and PowerBI)
  • Issues with Single Sign-on for Qlikview outstanding

Key Next Steps

  • Progress DTI034
  • Close DTI046
  • Prepare project brief for DTI047 in the light of re-priortisation

 

Overall the programme is rated at RED.

Issues with Qlikview Single Sign On and scope changes together wit time delays for DTI047.

 

Status and Forward Look

Resource Summary

 

Section Two: Projects Not Started

Project Info Project Manager's Commentary
     
     
     

Section Three: Projects in Progress

Project Info

Project Manager's Commentary  

 

 

 

 

DTI 034 - Qlik Implementation

 

Discretionary

Milestones

13/08/2018 Start

23-Nov-2018      Planning

21-Jun-2019      Delivery

1-Jul-2019      Project Closure

 

Report by Geoff Cropley for May 2019
 
Achievements this period
  • Further delays have been experienced with resolving Single Sign-on for Qlikview and this will delay the availability of Qlickview.  If there is no resolution throuth this process, users will use named user and password credentials
  • Remote Terminal Services has been requested to be able to demonstrate the Qlikview can be used in remote mode

Issues

  • None

Next Steps

  • Complete Single Sign-on ivestigations for Qlikview
  • Enable Single Sign-on for Qlicksense
  • Install Qlikview to support remote connectivity

RAG - Green

 

DTI046 - BI Framework

Discretionary

Milestones

Plan End of Planning 16-Nov-2018
Deliver Develop the Technical Strategy for BI Tools Service 31-Jan-2019
Deliver Design and Pilot Reporting Service 28-Feb-2019
Deliver Complete Delivery of BI Communications Plan 29-Mar-2019
Close Project Closure 19-Apr-2019

 

RAG

Green

Report by Geoff Cropley for May 2019

 

Achievements this period

All project deliverables completed.

Issues

None.

Next Steps

Close project.

RAG - Green

DTI 047 - BI Embed and Optimise

 

Discretionary

 

Milestones

Start:                         01/04/2019

End of Planning: 17/05/2019

Delivery:                19/07/2019

Completion:         31/07/2019

 
Report by Geoff Cropley for May 2019

Achievements this period

  • Programme re-prioritisation of deliverables has been completed and this has influenced the tasks to be included in the project
  • Confirmation from the sponsor has been sought and deliverables have been agreed

Issues

  • None

Next Steps

  • Continue with project deliverables
  • Produce revised estimate for time

 

RAG - Amber

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary