Report for June 2019
- Report Date
- May 2019
Report compiled by Geoff Cropley (Programme Manager)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
REPORT for June 2019
Key Achievements in Last Period
- QlikSense SSO completed (DTI034).
- Significant risk uncovered for EDW data access and connectivity for DTI047
- BI MI Project initiated (DTI049)
- Training for BI and Agile has been arranged
Top Issues
- Data accessibility of EDW delayed requiring a short term tactical solution while a long term strategic solution is found
Key Next Steps
- Progress DTI034
- Prepare project brief for DTI049
Overall the programme is rated at RED.
Issues with EDW access solutions together with time delays for DTI047. This is a major issue that has to be dealt with and the project is running out of time.
Status and Forward Look
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
|
|
|
|
DTI 034 - Qlik Implementation
Discretionary Milestones 13/08/2018 Start 23-Nov-2018 Planning 21-Jun-2019 Delivery 1-Jul-2019 Project Closure
|
Issues
Next Steps
RAG - Green
|
DTI 047 - BI Embed and Optimise
Discretionary
Milestones Start: 01/04/2019 End of Planning: 17/05/2019 Delivery: 19/07/2019 Completion: 31/07/2019 |
Achievements this period
Issues
Next Steps
RAG - Red |
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary | |
---|---|---|
DTI046 | Closed | |
Attachment | Size |
---|---|
![]() | 33.72 KB |
![]() | 36.07 KB |
![]() | 40.73 KB |