Report for Oct 2019
- Report Date
- October 2019
Programme Commentary
Overall the programme is AMBER.
Problem with long-term solution for EDW access and authorisations is unresolved
- short-term workaround agreed to allow access for EST109 Estates Strategic reporting UAT , and for testing of DTI049 HR datamart
Open issues with DTI034 and DTI047 have prevented these projects from being closed by planned closure date of 31-July 2019.
Key Achievements in Last Period
- DTI034- Conf call with Qlik & BME to agree LIVE architecture and configuration
- DTI047 - Prep and business requirements gathering for EDW data access and authorisations options appraisal workshop
Top Issues
- Need to agree a long-term solution for EDW access and authorisations, and any budget implication
- Need to deploy new Qlik services to LIVE
Key Next Steps
- DTI034 - Deploy new Qlik services to LIVE
- DTI047 - Complete options appraisal and secure funding to deliver recommended option
Status and Forward Look
Resource Summary to end of Oct 2019
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
DTI034 - Qlik Implementation
Discretionary
Milestones
Closure: Jan 2020 RAG - Amber |
Report by Jamie Thin for Oct 2019
Issues
|
DTI 047 - BI Embed and Optimise
Discretionary
Milestones
Closure: Jan 2020
RAG - Amber |
Achievements this period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary | |
---|---|---|
DTI046 - BI Framework Discretionary |
Geoff Cropley - closed
|
|