Report for Dec 2019
- Report Date
- December 2019
Programme Commentary
Overall the programme is AMBER.
Automated solution for EDW access and authorisation is not urgent. Existing manual solution is robust enough for the short term. Don't want to invest in automation until future usage patterns of EDW is better understood
Both DTI034 and DTI047 need additional funding to continue into 19/20 - this will come from the DTI BI/MI Programme and has been agreed with the DTI Portfolio Manager, Stephen Roy
Key Achievements in Last Period
- DTI034 - Qliksense hooked up to HR datamart on EDW in DEV. Prep for deploy to LIVE started
- DTI047 - EDW data access and authorisations options appraisal held and way forward agreed
Top Issues
- Need to agree a long-term solution for EDW access and authorisations considering both the Qlik and Power BI user communities, and any budget implication
- Need to deploy new Qlik services to LIVE
Key Next Steps
- DTI034 - Deploy new Qlik services to LIVE
- DTI047 - Complete options appraisal and secure funding to deliver recommended option
Status and Forward Look
Resource Summary to end of Dec 2019
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
DTI034 - Qlik Implementation
Discretionary
Milestones
Closure: Mar 2020 RAG - Amber |
Report by Jamie Thin for Dec 2019
|
DTI 047 - BI Embed and Optimise
Discretionary
Milestones
Closure: Mar 2020
RAG - Amber |
Achievements this period
Issues
Next Steps
RAG Commentary Amber Issue - need a steer on BI Tools strategy to align this project work with longer term strategy. Propose to fully support both Qliksense and Power BI. Need to agree business requirements to feed into estimate of development costs of the EDW Access and Authorisation solution. Some requirements will be agreed through a pilot with GASP |
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary | |
---|---|---|
DTI046 - BI Framework Discretionary |
Geoff Cropley - closed
|
|
Attachment | Size |
---|---|
BI Tools actual spend to end of DEC 2019 | 18.55 KB |
RAG status as at end of Dec 2019 | 24.39 KB |