Report for Feb 2020
- Report Date
- February 2020
Programme Commentary
Overall the programme is RED
The DTI047 project may need to be suspended unless the End of Planning project brief can be agreed within next month. DTI047 set to RED until this issue is resolved - delays to End of Planning relates to resource conflicts within IS Apps and changing priorities and emerging constraints when setting BI Tools strategic direction
Automated solution for EDW access and authorisation is not urgent. Existing manual solution is robust enough for the short term. UoE are best advised not to invest in automation until future usage patterns of EDW are better understood
Both DTI034 and DTI047 need additional funding to continue into 19/20 - this will come from the DTI BI/MI Programme and has been agreed with the DTI Portfolio Manager, Stephen Roy
Key Achievements in Last Period
- DTI034 - Qliksense upgraded to latest release, and new round of system testing in TEST in progress
- DTI047 - EDW data access and authorisations options appraisal completed and high-level S/W dev team design and rough cost estimate done
Top Issues
- Need to agree a long-term solution for EDW access and authorisations considering both the Qlik and Power BI user communities, and any budget implication
- Need to deploy new Qlik services to LIVE
Key Next Steps
- DTI034 - Deploy new Qlik services to LIVE
- DTI047 - Complete End of Planning
- DTI047 - Complete DTI047 deliverables
Status and Forward Look at end of Feb 2020
Resource Summary to end of Feb 2020
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
DTI034 - Qlik Implementation
Discretionary
Milestones
Closure: Mar 2020 RAG - AMBER |
Report by Jamie Thin for Feb 2020
|
DTI 047 - BI Embed and Optimise
Discretionary
Milestones
Closure: Mar 2020
RAG - RED |
Achievements this period
Issues
Next Steps
RAG Commentary - RED Issue - Resource conflict within project team , unfilled vacancies in IS Service Management team - End of Planning should be approved by 26-Feb 2020, or ISG PMO instruct that the project should be suspended. Business Impact - if project suspended and DTI047 deliverables are delayed, the launch of the HR datamart for HR Strategic reporting required for the People and Money programme will be delayed Action required - project stakeholders for DTI047, need to prioritise approving the End of Planning project brief w/c 24-Feb , over and above other competing activities. ISG SLT should prioritise approving PRAFs and enable vacancies to be filled quickly else there will be resource conflicts for project work
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary | |
---|---|---|
DTI046 - BI Framework Discretionary |
Geoff Cropley - closed
|
|
Attachment | Size |
---|---|
![]() | 23.56 KB |
![]() | 21.02 KB |