Report for December 2017
- Report Date
- December 2017
Report compiled by Nick Tordoff (Programme Manager) for Alex Carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Key Achievements in Last Period
- Further engagement with University stakeholders in Colleges and GASP.
- Approval to exit planning for Power BI project.
- Modelling of programme benefits aligned to the BI/MI Strategy
- Creation of initial Project Dossier
Top issues
- Access to Procurement for advice on potential procurement routes.
Key Next Steps
- Obtain approval to commence planning for projects to target project initiation at the start of January
- Set up meeting of BI Community stakeholder group
- Establish the framework for the stakeholder engagement event
- Agree tool procurement model
Status and Forward Look
Resource Summary
.
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
Qlikview Implementation | Planned Start Jun-18 | |
Tool 3 Implementation | Planned to start Aug-18 | |
Operational Reporting Requirements Analysis | Planned to start Aug-18 |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
HSS019- Power BI Gateway Service
Discretionary Milestones
RAG Green |
Report by Geoff Cropley for December 2017 Achievements this period Test environment build has been completed. The project is on track for a January 2018 deployment of the original deliverables. Issues None to report. Next Steps Continue with planned activities
|
DTI031 - Develop the BI Community
Discretionary Milestones
RAG Green |
Report by Nick Tordoff for December 2017 Achievements this period The project was approved to enter planning Issues None at this stage Next Steps Complete planning and commence delivery |
DTI032 - Business Reporting and Analytics Service Enhancements
Discretionary Milestones
RAG Green |
Report by Nick Tordoff for December 2017 Achievements this period The project was approved to enter planning Workshops with Service Management team to establish benefits and deliverables Recruitment of fixed term service manager to support new tools. Post commences at start of February Issues None at this stage Next Steps Complete planning and commence delivery |
DTI033 - Qlikview Consolidation
Discretionary Milestones
RAG Green |
Report by Nick Tordoff for December 2017 Achievements this period The project was approved to enter planning Issues None at this stage Next Steps Complete planning and commence procurement |
Section Four: Closed or Withdrawn Projects
None