The BI Tools programme is AMBER , budget for 20/21 has been agreed with People & Money
Status and Forward Look at end of Oct 2020 ( BI Tools within wider BI/MI Programme)
** add update **
Resource Summary to end of Oct 2020
Section Two: Projects Not Started
Project Info
Project Manager's Commentary
Section Three: Projects in Progress
Project Info
Project Manager's Commentary
DTI034 - Qlik Implementation
Discretionary
Milestones
Qlik Sense deploy to LIVE - 15-April - DONE
Qlikview CAHSS user and data migration - 22-April - DONE
Closure: Oct 2020
RAG - GREEN
Report by Jamie Thin for Aug 2020
Achievements this period
Qlik Sense pilot with GASP completed
Next Steps
Complete remaining project deliverables and handover to BAU teams
Close project
Issues
Qlikview - licence lease and QMC access issues when users run the services from their work laptops when working remotely
CAHSS users can not sign off the new Qlik view deployment until they can successfully connect remotely when working from home
DTI 047 - BI Embed and Optimise
Discretionary
Milestones
End of Planning:
28-Aug 2020 (Done)
RAG - AMBER
Report by Jamie Thin for Aug 2020
Achievements this period
Revised brief approved and End of Planning completed , the project will extend into 20/21
Agreed new minimum project brief to support launch of new HR Strategic reporting service in Dec 2020.
Issues
Additional business requirements need to be collected for support of both Qliksense and Power BI
Need to understand how the security model will be managed for the Finance datamart - it is expected that the BI team may need to deliver multiple different datamarts for different user groups
Next Steps
Dependency - Fine tune existing manual approach for EDW access and authorisation through a small pilot with GASP ( via DTI034)
Complete work to launch Service wrapper for the new EDW Datamarts
Launch full EDW service wrapper to provision service requests from BI Developers and MI Analysts from across the Schools, Colleges , Support Groups and other business units Close project
RAG Commentary - AMBER ISSUE
Issue - waiting for Budget for 20/21 to be agreed. Budget is transferring from ISG to People & Money (USG)