Report for May 2018
- Report Date
- May 2018
Report compiled by Chris Lawford (Programme Manager) for Alex Carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Key Achievements in Last Period
- Project Manager appointed for vital Qlik consolidation work.
- 17/18 budget: updated budget for programme agreed, proposal for additional spend submitted.
- Review of programme in progress with key stakeholders.
Top (Three) issues
- Ensure that the Qlikview Consolidation reaches a satisfactory conclusion. We must ensure that the project is compliant from both an IS and procurement perspective. We have identified the need for a procurement strategy, outline business case and procurement checklist, with a clear split across software products.
- Establish a clear scope for “DTI031 - Developing the BI Community” and decide how best to proceed.
- Define a clear scope for the rest of the programme, in-line with priorities and budget.
Key Next Steps
- Continue to conduct Programme review and ensure all elements are within governance and compliant.
- Complete negotiation of Qlik licences and reach award.
- Commence planning for Qlik implementation
- Agree scope and nature of community and reporting projects.
Overall, given the uncertainties, the programme is rated at AMBER.
Status and Forward Look
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
Qlikview Implementation | Planned Start May-18 | |
Enterprise Reporting Data Model | Planned to start March-18 | |
Operational Reporting Requirements Analysis | Planned to start Aug-18 |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
HSS019- Power BI Gateway Service
Discretionary Milestones 20-Apr-2018 Project Closure RAG BLUE |
Report by Geoff Cropley for May 2018 Achievements this periodProject has completed successfully and is now closed. IssuesNone
Next StepsNone
|
DTI031 - Develop the BI Community
Discretionary Milestones 02-Feb-2018 Exit Planning 14-Jul-2018 Project Delivery 28-Jul-2018 Project Closure RAG Amber |
Report by Chris Lawford for May 2018 Discussed at BIT board meeting 23/05. Withdrawal of project not approved, as the objectives are clearly mentioned within the remit for the programme. However, the difficulty in framing project scope with a clear set of deliverables was acknowledged. Proper scope definition required. Must result in an actionable plan, either as a project, or a BAU activity. Achievements this period
Issues
Next Steps
The project is reporting a status of AMBER |
DTI032 - Business Reporting and Analytics Service Enhancements
Discretionary Milestones 16-Mar-2018 End of Planning 23-Mar-2018 Service Enhancement Review 21-Apr-2018 Target Operating Model 27-Apr-2018 Small Change Process 18-May-2018 Security Policy Review 31-May-2018 End User Training Review 15-Jun-2018 Project Closure RAG Green |
Report by Geoff Cropley for May 2018 Achievements this periodService Review, Target Operating and Security streams have completed. IssuesNone Next StepsContinue delivery to agreed milestones. Training Assessment and Augment target operating model supporting Power BI. |
DTI033 - Qlikview Consolidation
Discretionary Milestones 26-Jan-2018 Exit Planning 09-Feb-2018 Issue Requirements to the Vendor 09-Mar-2018 Issue Purchase Order 16-Mar-2018 Project Completion 30-Mar-2018 Project Closure
RAG Amber |
Report by Craig Moore for May 2018 Achievements
Issues
Next StepsCreation of,
|
Section Four: Closed or Withdrawn Projects
None