Report for May 2018

Report Date
May 2018

Report compiled by  Chris Lawford (Programme Manager) for Alex Carter (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

Programme Commentary

Key Achievements in Last Period

  • Project Manager appointed for vital Qlik consolidation work. 
  • 17/18 budget: updated budget for programme agreed, proposal for additional spend submitted.
  • Review of programme in progress with key stakeholders.  

Top (Three) issues

  • Ensure that the Qlikview Consolidation reaches a satisfactory conclusion. We must ensure that the project is compliant from both an IS and procurement perspective. We have identified the need for a procurement strategy, outline business case and procurement checklist, with a clear split across software products.
  • Establish a clear scope for “DTI031 - Developing the BI Community” and decide how best to proceed.
  • Define a clear scope for the rest of the programme, in-line with priorities and budget.    

Key Next Steps

  • Continue to conduct Programme review and ensure all elements are within governance and compliant.
  • Complete negotiation of Qlik licences and reach award.
  • Commence planning for Qlik implementation
  • Agree scope and nature of community and reporting projects.

Overall, given the uncertainties, the programme is rated at AMBER.

Status and Forward Look

Resource Summary

Section Two: Projects Not Started

Project Info Project Manager's Commentary
Qlikview Implementation  Planned Start May-18  
Enterprise Reporting Data Model  Planned to start March-18  
Operational Reporting Requirements Analysis Planned to start Aug-18  

Section Three: Projects in Progress

Project Info

Project Manager's Commentary  

HSS019- Power BI Gateway Service

 

 

 

Discretionary

Milestones

20-Apr-2018    Project Closure       

RAG

BLUE

Report by Geoff Cropley for May  2018

Achievements this period

Project has completed successfully and is now closed.

Issues

None

 

Next Steps

None

 

DTI031 - Develop the BI Community

 

 

 

Discretionary

Milestones

02-Feb-2018 Exit Planning

14-Jul-2018         Project Delivery

28-Jul-2018         Project Closure   

RAG

Amber

Report by Chris Lawford for May  2018

Discussed at BIT board meeting 23/05. Withdrawal of project not approved, as the objectives are clearly mentioned within the remit for the programme. However, the difficulty in framing project scope with a clear set of deliverables was acknowledged. Proper scope definition required. Must result in an actionable plan, either as a project, or a BAU activity. 

Achievements this period

  • None

Issues

  • See above

Next Steps

  • Review scope, re-define or withdraw project.

The project is reporting a status of AMBER

DTI032 - Business Reporting and Analytics Service Enhancements

 

Discretionary

Milestones

16-Mar-2018 End of Planning 

 23-Mar-2018 Service Enhancement Review

 21-Apr-2018 Target Operating Model

 27-Apr-2018 Small Change Process

 18-May-2018 Security Policy Review

 31-May-2018 End User Training Review

 15-Jun-2018 Project Closure   

RAG

Green

Report by Geoff Cropley for May 2018

Achievements this period

Service Review, Target Operating and Security streams have completed. 

Issues

None

Next Steps

Continue delivery to agreed milestones. Training Assessment and Augment target operating model supporting Power BI.

DTI033 - Qlikview Consolidation

 

Discretionary

Milestones

26-Jan-2018        Exit Planning

09-Feb-2018       Issue Requirements to the Vendor

09-Mar-2018      Issue Purchase Order

16-Mar-2018      Project Completion

30-Mar-2018      Project Closure

  

RAG

Amber

Report by Craig Moore for May 2018

Achievements

  • Process of discovery by the new Programme Manager and Project Manger has now been completed. An assessment has been made regarding the progress made by the previous Programme/ Project Manager.
  • Communications have been reestablished with the vendors and revised quotes requested.
  • New ProM and PM in situ

Issues

  • The project is in a process of untangling the quotes for QlikView and Qlik Sense as the known business justification is stronger for QlikView.
  • The business case must be formulated and presented for sign-off.
  • PICCL needs to be raised to extend the budget for internal resources.
  • PICCL needs to be raised to rebaseline the milestones.

Next Steps

Creation of,

  • Business Case
  • Technical Procurement Checklist
  • Procurement Strategy

 

 

 

 

Section Four: Closed or Withdrawn Projects

None

 