Report for June 2018
- Report Date
- June 2018
Report compiled by Chris Lawford (Programme Manager) for Alex Carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Key Achievements in Last Period
- Qlikview Consolidation: Ongoing, regular discussions with supplier and stakeholders. Draft procurement artefacts in advanced stages of preparation.
- Reporting & Analytics service - project progressing as planned.
- Planning for 18/19 in progress.
Top Issues
- Qlikview Consolidation. Reach award.
- Establish a clear scope for “DTI031 - Developing the BI Community” and decide how best to proceed.
- Agree a plan for 18/19 deliverables and budget.
Key Next Steps
- Qlikview Consolidation: Issue procurement artefacts and gain approvals. Sign contract.
- Commence planning for Qlik implementation
- Agree scope and nature of community and 18/19 projects.
Overall, given the uncertainties, the programme is rated at AMBER.
Status and Forward Look
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
Qlikview Implementation | Planned Start May-18 | |
Enterprise Reporting Data Model | Planned to start March-18 | |
Operational Reporting Requirements Analysis | Planned to start Aug-18 |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||||||||||
DTI031 - Develop the BI Community
Discretionary Milestones 02-Feb-2018 Exit Planning 14-Jul-2018 Project Delivery 28-Jul-2018 Project Closure RAG Amber |
Report by Chris Lawford for Jun 2018 Discussed at BIT board meeting 23/05. Withdrawal of project not approved, as the objectives are clearly mentioned within the remit for the programme. However, the difficulty in framing project scope with a clear set of deliverables was acknowledged. Proper scope definition required. Must result in an actionable plan, either as a project, or a BAU activity. Action item is with service mgmt to propose a new scope. Achievements this period
Issues
Next Steps
The project is reporting a status of AMBER. |
||||||||||||||||
DTI032 - Business Reporting and Analytics Service Enhancements
Discretionary Milestones
RAG Green |
Report by Geoff Cropley for June 2018 Achievements this periodPower BI target operating model underway. Training collateral review commenced. IssuesNone Next StepsComplete project deliverables during July including Power BI target operating model and training collateral review. |
||||||||||||||||
DTI033 - Qlikview Consolidation
Discretionary Milestones 26-Jan-2018 Exit Planning 09-Feb-2018 Issue Requirements to the Vendor 09-Mar-2018 Issue Purchase Order 16-Mar-2018 Project Completion 30-Mar-2018 Project Closure
RAG Amber |
Report by Craig Moore for June 2018 Achievements
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary | |
---|---|---|
HSS019 - Power BI Gateway | Project Closed | |
Attachment | Size |
---|---|
![]() | 26.3 KB |
![]() | 32.21 KB |