Report for September 2018

Report Date
September 2018

Highlights This Period

  • DTI030 - Define Document Management Service
    • Project closed

 

  •  Priorities Next Period (October 2018)
  • Complete handover to the new Document Management Programme Manager - Hilary Shand
  •  

Overall, the programme is reporting GREEN. There is currently no projects in progress or scheduled to commence

RAG Status and Forward Look

Resource Summary

 

The programme consists of:

  1. DTI030– Define Document Management Service – closed
  2. DTI041– Develop and Deploy Document Management System – Not started.
  3. DTI042– Show Case Template Service for Document Management System – Project withdrawn (agreed WIS 20/04/18)
  4. DTI043– Embed and Optimise Document Management System --- Not started

 

Projects & deliverables

Projects

Deliverables (Main Components)

DTI030– Define Document Management Service

 

Discretionary

Milestones

Stage Milestone Due Date
     
     

 

RAG

Blue:

 

Report by Andrew Stewart for September 2018

Achievements in Last Period

  • Project report approved by the project board
  • Project closure report approved
  • Project closed at WIS on 28/09/18

Issues

  • None

Next Steps 

  • None

DTI041– Develop and Deploy Document Management System

 

Discretionary

Milestones

Target Date

Title                    

                                

 

RAG

Green (Not Started)

Report by Andrew Stewart for September 2018

Achievements in Last Period

  • None
  •  

Issues

  • None

Next Steps 

  • None
AttachmentSize
Image icon 201808-rag.png22.1 KB
Image icon 201808a-rag.png19.19 KB
Image icon 201809-rag.png17.47 KB