DMS Programme Reporting for March 2018

Report Date
March 2018

Highlights This Period

  • DTI030 planning milestone achieved and agreed;
  • Resources have joined and been through engagement processes;
  • Requirements for DTI042 were included as objectives in DTI030 and DTI041, project can be suspended;
  • Communications strategy being implemented with portal, web sites and communications tools in place.

 Priorities Next Period (April/May 2018)

  • Identification of the teams and resources that will provide requirements information;
  • Capture of requirements;
  • Identification of methods for requirements ranking and for defining the service coverage;
  • Set-up requirements meetings for analysis and agreement of priorities;
  • Next programme board meeting scheduled for 02/05/18;

Key Programme Risks and Issues:

  • Programme Risk 3 – There is a risk that the Document Management service will be unsustainable following the end of the Digital Transformation funding. This will become clearer once requirements are defined.
  • Programme Risk 7 – There is a risk that the scope for work being funded by Digital Transformation is unclear. Work being done to clarify.
  • Programme Risk 8 – There is a risk that there is insufficient user engagement. The communications plan will be designed to mitigate.
  • Programme Risk 9 – There is a risk that the work is insufficiently informed by external best practice. External services are being engaged to mitigate.
  • Programme Risk 10 – There is a risk that there is a loss of trust and engagement through slow delivery. The communications plan and the potential for showcase services are being investigated to mitigate.
  • Programme Risk 11 – There is a risk that there are unclear boundaries with Core Systems DMS work. Engagement with CS delivery teams underway to mitigate.
  • Programme Risk 12 – There is a risk that the project generates undeliverable demand for DMS. This will be defined with the requirements expression.
  • Programme Risk 13 – There is a risk that there is a failure to engage senior management. The communications plan and the potential for showcase services are being investigated to mitigate.
  • Programme Risk 14 – There is a risk that there is not enough leadership capacity in Service Management. Mitigation is to ensure DD/CH/AC all used as a pool of resources.
  • Programme Risk 15 – There is a risk that there is a reliance on contractors and other short term resources. Mitigation underway with initial recruitment.
  • Programme Risk 16 – There is a risk that there is ineffective programme level governance. Programme Manager putting governance mechanisms in place now.
  • Programme Risk 17 – There is a risk that fragmentation and confusion are introduced by non Digital Transformation project and BAU service SharePoint activities.

RAG Status and Forward Look

Resource Summary

The above table was taken as planning data was being added to asta. DTI030 has a budget of 275 days and some of the days lodged against DTIP07 will be transferred to DTI030 for the SharePoint consultant time lodged against the programme instead of against the project.

The programme consists of:

  1. DTI030– Define Document Management Service – Project has finished planning and design stage is well underway.
  2. DTI041– Develop and Deploy Document Management System – Project documentation being drafted
  3. DTI042– Show Case Template Service for Document Management System – Project will be suspended as requirements now part of DTI030 and DTI041;
  4. DTI043– Embed and Optimise Document Management System --- Initiation documentation being done but project not to commence this  financial period

 

Projects & deliverables

Projects

Deliverables (Main Components)

DTI030– Define Document Management Service

 

Discretionary

Milestones

Target Date

Title                    

 

30-Mar-2018   

21-Mar-2018

 

01-Jun-2018

29-Jun-2018

27-Jul-2018

 

                                

End of Planning

Review of requirements for ranking;

Complete Requirements Gathering;

Deliver Service Definition;

Closure Review;

 

RAG

GREEN

Report by Don MacIver for March 2018

  • Statement of requirements with use cases for service
  • Recommendations based on review of third party tools
  • Business case for adoption of third party tools that are considered essential
  • Service definition for DMS
  • Costed plans to build and implement the service
  • Communications and engagement plan

Achievements in Last Period

  • Staff engaged
  • Planning set out and agreed with team
  • Communications developed and ready to release first communications
  • Plan and brief submitted to WIS and agreed.
  • Web presence for DT and for DMS specifically created.
  • Initial meeting for Showcase deliverable

Next Steps 

  • Start communications with internal and external bodies
  • Gather requirements and engage with stakeholders
  • Add to web site content for reference
  • Initiate non-targeted communications via blogs, news-sheets etc.

DTI041– Develop and Deploy Document Management System

 

Discretionary

Milestones

Target Date

Title                    

01-May-2018                                   

Start-up

RAG

n/a as Not Started

Report by Don MacIver for March 2018

  • Analysis of SharePoint capability based on the business requirements
  • Defined use cases for SharePoint
  • DMS Toolkit created
  • Procure and implement any essential add-on tools including any required POC and transition to business as usual. Testing and POCs
  • Training, documentation and marketing materials
  • User forum
  • Sales strategy

Achievements in Last Period

  • None
  • Issues
    • None

Next Steps 

  • Submit initiation report to WIS
  • Produce and Agree Brief 

DTI042– Show Case Template Service for Document Management System

 

Discretionary

Milestones

Target Date

Title                    

01-May-2018                                   

Start-up

RAG

n/a as not started

Report by Don MacIver for March 2018

  • Produce a SharePoint DMS showcase to demonstrate capabilities and toolset.
  • Using specific DMS use cases, identify products that will provide benefit and will be drawn into final solution, provide tangible benefits and give a demonstrable suite of components that can be quickly adapted to other DMS requirements.

Achievements in Last Period

  • Project objectives transferred to DTI030 and DTI041.
  • Issues
    • None

Next Steps 

  • Submit PICCL to WIS to suspend

DTI043– Embed and Optimise Document Management System

Discretionary

Milestones

Target Date

Title                    

01-Mar-2019                                   

Start-up

RAG

n/a as Not Started

Report by Don MacIver for March 2018

  • Review success criteria, targets and measures of the newly launched Document Management Service and implement any changes identified. 
  • Provide further recommendations;
  • Identify specifications for future projects will be identified including recommendation of any essential add-ons (if future funding secured).

Achievements in Last Period

  • None
  • Issues
    • None

Next Steps 

  • Produce and agree Brief
  • Submit initiation report to WIS 

 