DMS Programme Reporting for April 2018
- Report Date
- April 2018
Highlights This Period
- DTI030 had commenced against agreed plan but progress meetings highlighted resource availability was not as planned(see programme risk and PICCL );
- DTI042 was withdrawn (agreed WIS 20/04/18);
- Communication plan progressing well and providing the candidates for requirements workshops.
- Publications for blogs and news-sheets published;
- DMS portal in place with FAQ, background, contact information and news. Web site for Digital Transformation has been updated for DMS.
- Initial template for PM Showcase has been shared with PMO.
Priorities Next Period (May/June 2018)
- Re-plan of DTI030 and DTI041 when resource availability has been clarified (due 04/05/18). Tasks will include:
-
Refining the structure of the deliverable and agree the form of the reports to be produced;
- Stakeholder Workshops:
- Review contacts and confirm schedule for workshops;
- Define engagement based on candidate responses to engagement questionnaire;
- Implement the requirements workshops using requirements tools appropriate for groups identified using the questionnaire responses;
- Based on above, agree which method used for requirements ranking and service definition;
- External Document Management Services best-practice review and report preparation;
-
- Next programme board meeting scheduled for 02/05/18;
Key Programme Risks and Issues:
1 |
RED |
Reduce |
||
3 |
AMBER |
Reduce |
||
7 |
Unclear scope for work being funded by Digital Transformation |
AMBER |
Reduce |
|
8 |
AMBER |
Reduce |
||
12 |
Work generates undeliverable demand for Document Management services |
AMBER |
Reduce |
|
13 |
AMBER |
Reduce |
||
14 |
AMBER |
Reduce |
||
15 |
AMBER |
Reduce |
||
16 |
AMBER |
Reduce |
||
17 |
AMBER |
Reduce |
RAG Status and Forward Look
Resource Summary
The programme consists of:
- DTI030– Define Document Management Service – Planning was agreed and signed off. Resource availability has moved the project to a Red state.
- DTI041– Develop and Deploy Document Management System – Project documentation being drafted. Impact on DTI030 means there will not be requirements or resources to start as planned.
- DTI042– Show Case Template Service for Document Management System – Project withdrawn (agreed WIS 20/04/18);
- DTI043– Embed and Optimise Document Management System --- Initiation documentation being done but project not to commence this financial period
Projects & deliverables
Projects |
Deliverables (Main Components) |
||||
DTI030– Define Document Management Service
Discretionary Milestones
RAG RED |
Report by Don MacIver for April 2018
Achievements in Last Period
Next Steps
|
||||
DTI041– Develop and Deploy Document Management System
Discretionary Milestones
RAG RED (Not Started) |
Report by Don MacIver for April 2018
Achievements in Last Period
Next Steps
|
||||
DTI042– Show Case Template Service for Document Management System
Discretionary Milestones
RAG n/a Withdrawn (agreed WIS 20/04/18) |
Report by Don MacIver for April 2018
Achievements in Last Period
Next Steps
|
||||
DTI043– Embed and Optimise Document Management System Discretionary Milestones
RAG Green (Not Started) |
Report by Don MacIver for April 2018
Achievements in Last Period
Next Steps
|