DMS Programme Reporting for April 2018

Report Date
April 2018

Highlights This Period

  • DTI030 had commenced against agreed plan but progress meetings highlighted resource availability was not as planned(see programme risk  and PICCL );
  • DTI042 was withdrawn (agreed WIS 20/04/18);
  • Communication plan progressing well and providing the candidates for requirements workshops
  • Publications for blogs and news-sheets published;
  • DMS portal in place with FAQ, background, contact information and news. Web site for Digital Transformation has been updated for DMS.
  • Initial template for PM Showcase has been shared with PMO.

 Priorities Next Period (May/June 2018)

  •  Re-plan of DTI030 and DTI041 when resource availability has been clarified (due 04/05/18). Tasks will include:
    • Refining the structure of the deliverable and agree the form of the reports to be produced;

      • Stakeholder Workshops:
      • Review contacts and confirm schedule for workshops;
      • Define engagement based on candidate responses to engagement questionnaire;
      • Implement the requirements workshops using requirements tools appropriate for groups identified using the questionnaire responses;
    • Based on above, agree which method used for requirements ranking and service definition;
    • External Document Management Services best-practice review and report preparation;
  • Next programme board meeting scheduled for 02/05/18;

Key Programme Risks and Issues:

Ref

Title

Current Risk

Management Approach

Risk Owner

1

Service Management unable to deliver the required effort in the compressed time period of January to July 2018

RED

Reduce

Don MacIver

3

Document Management service will be unsustainable following the end of the Digital Transformation funding

AMBER

Reduce

Alex Carter

7

Unclear scope for work being funded by Digital Transformation

AMBER

Reduce

Catherine Hetherington

8

Insufficient user engagement

AMBER

Reduce

Catherine Hetherington

12

Work generates undeliverable demand for Document Management services

AMBER

Reduce

Catherine Hetherington

13

Failure to engage senior management

AMBER

Reduce

Mark Ritchie

14

Availability of Service Management leadership team

AMBER

Reduce

Alex Carter

15

Reliance on contractors and other short term resources

AMBER

Reduce

Catherine Hetherington

16

Ineffective programme level governance

AMBER

Reduce

Mark Ritchie

17

Fragmentation and confusion introduced by non Digital Transformation project and BAU service SharePoint activities

AMBER

Reduce

Catherine Hetherington

 

RAG Status and Forward Look

Resource Summary

 

The programme consists of:

  1. DTI030– Define Document Management Service – Planning was agreed and signed off. Resource availability has moved the project to a Red state.
  2. DTI041– Develop and Deploy Document Management System – Project documentation being drafted. Impact on DTI030 means there will not be requirements or resources to start as planned.
  3. DTI042– Show Case Template Service for Document Management System – Project withdrawn (agreed WIS 20/04/18);
  4. DTI043– Embed and Optimise Document Management System --- Initiation documentation being done but project not to commence this  financial period

 

Projects & deliverables

Projects

Deliverables (Main Components)

DTI030– Define Document Management Service

 

Discretionary

Milestones

Target Date

Title                    

 

30-Mar-2018   

21-Mar-2018

 

01-Jun-2018

29-Jun-2018

27-Jul-2018

 

                                

End of Planning (Done)

Review of requirements for ranking;

Complete Requirements Gathering;

Deliver Service Definition;

Closure Review;

 

RAG

RED

Report by Don MacIver for April 2018

  • Statement of requirements with use cases for service
  • Recommendations based on review of third party tools
  • Business case for adoption of third party tools that are considered essential
  • Service definition for DMS
  • Costed plans to build and implement the service
  • Communications and engagement plan

Achievements in Last Period

  •  DTI030 planning milestone completed and agreed;
  • Plan being progressed ;
  • Communication plan is in progress and engagement has been generated. This will provide the delegate lists for workshops. 
  • DMS portal in place with FAQ, background, contact information and news. Web site for Digital Transformation has been updated for DMS.
  • Initial template for Project Management Showcase has been shared.

Next Steps 

  •  Re-planning when resource availability has been clarified (due 04/05/18):
    • Refine structure of the deliverable and agree the form of the reports to be produced;
    • Review contacts provided and confirm schedule for workshops;
    • Start stakeholder workshops and requirements collection:
    • Define engagement based on candidate responses to engagement questionnaire;
    • Schedule the requirements workshops and identify requirements tools appropriate for delegates using their questionnaire responses;
    • Based on above, agree which method used for requirements ranking and service definition;
    • External Document Management Services best-practice review and report preparation;
    • Further broad communications via blogs, newsheets etc.

DTI041– Develop and Deploy Document Management System

 

Discretionary

Milestones

Target Date

Title                    

07-May-2018                                   

Start-up

RAG

RED (Not Started)

Report by Don MacIver for April 2018

  • Analysis of SharePoint capability based on the business requirements
  • Defined use cases for SharePoint
  • DMS Toolkit created
  • Procure and implement any essential add-on tools including any required Proof of Concept and transition to business as usual. Testing and PoCs.
  • Training, documentation and marketing materials
  • User forum
  • Sales strategy

Achievements in Last Period

  • None
  • Issues
    • PICCL in DTI030 and Programme Risk 1 impact resources and requirements for the project.

Next Steps 

  • Submit initiation report to WIS
  • Produce and Agree Brief 

DTI042– Show Case Template Service for Document Management System

 

Discretionary

Milestones

Target Date

Title                    

n/a                                

 

RAG

n/a  Withdrawn (agreed WIS 20/04/18)

Report by Don MacIver for April 2018

  • Produce a SharePoint DMS showcase to demonstrate capabilities and toolset.
  • This project was superseded by deliverable in DTI030 and DTI041.

Achievements in Last Period

  • Withdrawn (agreed WIS 20/04/18)
  • Issues
    • None

Next Steps 

  • n/a

DTI043– Embed and Optimise Document Management System

Discretionary

Milestones

Target Date

Title                    

01-Mar-2019                                   

Start-up

 

RAG

Green (Not Started)

Report by Don MacIver for April 2018

  • Review success criteria, targets and measures of the newly launched Document Management Service and implement any changes identified. 
  • Provide further recommendations;
  • Identify specifications for future projects will be identified including recommendation of any essential add-ons (if future funding secured).

Achievements in Last Period

  • None
  • Issues
    • None

Next Steps 

  • Produce and agree Brief
  • Submit initiation report to WIS 