Report for May 2018
- Report Date
- May 2018
Highlights This Period
-
Mitigations were put in place to address the resourcing impact on DTI030. Project moved to Amber as plan in place to reflect the following:
- DTI041 initiation was delayed;
- PICCL raised to engage UX team;
- Programme management engaged additionally with the project to assist and student resource also made available.
- PICCL agreed for new milestone dates aligned with resources engaged and plan progressed (see programme risk and PICCL );
- Communication plan progressed and invitations are out with the first workshops taking place next week.
- Initial template for PM Showcase has been shared with PMO.
Priorities Next Period (June/July 2018)
- Review and agree the drafts of the reports to be produced;
- Carry out Stakeholder Workshops with additional effort from UX team as proposed;
- Gather further requirements and identify candidates from the pipeline of SharePoint work that would benefit our requirements gathering as case-studies.
- Based on above, agree which method used for requirements ranking and service definition;
- External Document Management Services best-practice review and report preparation;
- Programme planning for FY18/19 i.e. DTI041 and DTI043.
- Programme board meeting took place on 05/06/18;
Key Programme Risks and Issues:
1 |
AMBER |
Reduce |
||
3 |
AMBER |
Reduce |
||
7 |
Unclear scope for work being funded by Digital Transformation |
AMBER |
Reduce |
|
13 |
AMBER |
Reduce |
||
14 |
AMBER |
Reduce |
||
15 |
AMBER |
Reduce |
||
17 |
AMBER |
Reduce |
||
18 | RMS impact from DMS programme engagement | AMBER | Reduce | Tracey Slaven |
RAG Status and Forward Look
Resource Summary
The programme consists of:
- DTI030– Define Document Management Service – In Design after replanning.
- DTI041– Develop and Deploy Document Management System – Not started.
- DTI042– Show Case Template Service for Document Management System – Project withdrawn (agreed WIS 20/04/18);
- DTI043– Embed and Optimise Document Management System --- Initiation documentation being done but project not to commence this financial period
Projects & deliverables
Projects |
Deliverables (Main Components) |
||||
DTI030– Define Document Management Service
Discretionary Milestones
RAG AMBER
|
Report by Don MacIver for May 2018
Achievements in Last Period
Next Steps
|
||||
DTI041– Develop and Deploy Document Management System
Discretionary Milestones
RAG Green (Not Started) |
Report by Don MacIver for May 2018
Achievements in Last Period
Next Steps
|
||||
DTI042– Show Case Template Service for Document Management System
Discretionary Milestones
RAG n/a Withdrawn (agreed WIS 20/04/18) |
Report by Don MacIver for May 2018
Achievements in Last Period
Next Steps
|
||||
DTI043– Embed and Optimise Document Management System Discretionary Milestones
RAG Green (Not Started) |
Report by Don MacIver for May 2018