Report for June 2018 *DRAFT*

Report Date
June 2018

Highlights This Period

  • The User Experience brief was agreed and approved and a workshop was held

  • The Business Requirements Stakeholder workshops were held
  • The new Project Manager (Barry Ure) for DTI030 started on 18th June and project handover completed
  • Initiated the implementation phase of the Communication plan to  engage key stakeholders and support requirements gathering. 
  • Programme Board meeting held on 5th June.
  • Sharepoint SME resource issues largely addressed but resource situation will require monitoring

 

  •  Priorities Next Period (July/August 2018)
  • Complete recruitment of the replacement Document Management Programme Manager
  • Review and agree the drafts of the reports to be produced;
  • Identify candidates from the pipeline of SharePoint work that would benefit our requirements gathering as case-studies.
  • Agree which method used for requirements ranking and service definition;
  • External Document Management Services best-practice review and report preparation;
  • Programme planning for FY18/19 i.e. DTI041 and DTI043 (to be completed by the new Programme Manager when in role)

Overall, the programme is reporting AMBER due to delays caused by the previous re-allocation of SME Sharepoint expertise at short notice.  This has pushed back the delivery milestones by approximately 6.5 weeks, and will increase programme delivery and budget pressure in 2018/19.

RAG Status and Forward Look

Resource Summary

 

The programme consists of:

  1. DTI030– Define Document Management Service – completed planning, in design.
  2. DTI041– Develop and Deploy Document Management System – Not started. (Due to start in 2019.)
  3. DTI042– Show Case Template Service for Document Management System – Project withdrawn (agreed WIS 20/04/18);
  4. DTI043– Embed and Optimise Document Management System --- Initiation documentation being done but project not to commence this  financial period

 

 

Projects & deliverables

Projects

Deliverables (Main Components)

DTI030– Define Document Management Service

 

Discretionary

Milestones

Target Date

Title                    

30-Mar-2018   

09-Jul-2018

16-Jul-2018

23-Jul-2018

27-Jul-2018                          

 

End of Planning (Done)

Review of requirements for ranking;

Complete Requirements Gathering;

Deliver Service Definition;

Closure Review;

 

RAG

AMBER

 

Report by Barry Ure for June 2018

Achievements in Last Period

  • Statement of requirements with use cases for service
  • Recommendations based on review of third party tools
  • Business case for adoption of third party tools that are considered essential
  • Service definition for DMS
  • Costed plans to build and implement the service
  • Communications and engagement plan

 

Next Steps 

  • Commence the workshops w/c 11/06/18. Rooms booked and event management in place for  delegates to choose initial workshop to attend.
  • Gather the information for the reports to be produced;
  • Review contacts provided and confirm schedule for remaining workshops;
  • Based on above, agree which method used for requirements ranking and service definition;
  • External Document Management Services best-practice review and report preparation;
  • Further broad communications via blogs, newsheets etc.

DTI041– Develop and Deploy Document Management System

 

Discretionary

Milestones

Target Date

Title                    

15-Aug-2018                                   

Start

RAG

Green (Not Started)

Report by Barry Ure for June 2018

  • Analysis of SharePoint capability based on the business requirements
  • Defined use cases for SharePoint
  • DMS Toolkit created
  • Procure and implement any essential add-on tools including any required Proof of Concept and transition to business as usual. Testing and PoCs.
  • Training, documentation and marketing materials
  • User forum
  • Sales strategy

Achievements in Last Period

  • PICCL to delay start submitted. 
  • Issues
    • N/A

Next Steps 

  • Submit initiation report to WIS
  • Produce and Agree Brief 

DTI042– Show Case Template Service for Document Management System

 

Discretionary

Milestones

Target Date

Title                    

n/a                                

 

RAG

n/a  Withdrawn (agreed WIS 20/04/18)

Report for June 2018

  • Produce a SharePoint DMS showcase to demonstrate capabilities and toolset.
  • This project was superceded by deliverable in DTI030 and DTI041.

Achievements in Last Period

  • Withdrawn (agreed WIS 20/04/18)
  • Issues
    • None

Next Steps 

  • n/a

DTI043– Embed and Optimise Document Management System

Discretionary

Milestones

Target Date

Title                    

01-Mar-2019                                   

Start

 

RAG

Green (Not Started)

Report for June 2018

  • Review success criteria, targets and measures of the newly launched Document Management Service and implement any changes identified. 
  • Provide further recommendations;
  • Identify specifications for future projects will be identified including recommendation of any essential add-ons (if future funding secured).

Achievements in Last Period

  • None
  • Issues
    • None

Next Steps 

  • Produce and agree Brief
  • Submit initiation report to WIS 
AttachmentSize