Report for January 2018
- Report Date
- January 2018
Report compiled by Chris Lawford (Programme Manager) for Alex carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Key Achievements in Last Period
- EDW DEV environment build still in progress. Target now 09/02.
- ETL Procurement: ITT responses received and under review.
- Draft development guidelines created and under review.
- Communication strategy & plan, governance strategy & plan, migration plan delivered.
- BIMI Service RACI – first draft created and under review.
- Mid-year review conducted and proposal for 18/19 created.
- Sustainability plan created and under review.
Top 3 issues
- Delays in EDW build process.
- Limit the knock-on effects of any delays in ETL procurement.
- Funding approval for Oracle Advanced Security, in order conform with EDW security policy.
Key Next Steps
- Closely monitor DEV build progress.
The programme continues to report AMBER - due to the underlying project statuses.
Status and Forward Look
For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
DTI005 ETL Tool Implementation |
Planned to start Apr-18 | |
DTI021 EDW Embed & Optimise |
Planned to start Apr-18 |
|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||||
DTI004 - ETL Tool Procurement
Discretionary Milestones 15-Dec-2017 ITT Issued 28-Mar-2018 Project Delivery 13-Apr-2018 Project Close RAG GREEN |
Report by Nick Graham for January 2018 Achievements in Last Period
Issues
Next Steps
The project is reporting GREEN.
|
||||||||||
DTI006 - EDW Implementation
Discretionary Milestones 12-MAR-18 Org Hierarchy ASOR 13-APR-18 Infrastructure Build Complete 20-APR-18 Deployment 07-MAY-18 Project Close RAG AMBER |
Report by Chris Lawford for January 2018 Achievements in Last Period
Issues
Next Steps
The project is currently reporting AMBER, due to the late delivery of Dev infrastructure.
|
||||||||||
DTI019 - BI/MI Analysis Toolkit
Discretionary Milestones
RAG GREEN |
Report by Sue Woodger for January 2018 Achievements
Issues
Next Steps
Project is green as new dates have been approved |
||||||||||
DTI022 - EDW Business Engagement
Discretionary Milestones 15-SEP-17 Planning Complete 24-JAN-18 Project Delivery 31-JAN-18 Project Close RAG GREEN |
Report by Geoff Cropley for January 2018 Achievements in Last PeriodAs part of the communications schedule a lunchtime seminar was held focusing on the need for EDW governance and project pipeline planning. All project deliverables have been completed and handover to the business owner is underway. Project closure is expected to complete 20th February. IssuesNone to report Next StepsSign off all deliverables for Communications, Governance and Business Engagement. Handover outcomes to business owner. |
Section Four: Closed or Withdrawn Projects
DTI003 Withdrawn
COM029 Proof of concept project has now been closed.