Report for March 2018
- Report Date
- March 2018
Report compiled by Chris Lawford (Programme Manager) for Alex carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Key Achievements in Last Period
- EDW TEST build started. Good progress being made.
- Org/Hierarchy development phase complete and deployed to DEV.
- ETL Procurement: contract award process underway; project initiation for implementation phase submitted.
- BI/MI Organisation RACIs “Run the Service” & “Change the service” drafts complete. “Small Changes” workshop planned for April.
- Funding model approved for Oracle Advanced Security Option.
Top Three issues
- Maintaining progress on EDW infrastructure build.
- Reaching ETL contract award and expediting implementation project.
- Management of Overspend on ETL Procurement (c.30 days).
- Achieving project closures on DTI019: BI/MI Analysis Tool-kit and DTI022: EDW Business Engagement
Key Next Steps
- Complete TEST infrastructure build, commence LIVE.
- Award of ETL contract, planning & kick-off of the implementation project.
- Achieving project closures for BI/MI Analysis Tool-kit, EDW Business Engagement
- Approval of 18/19 Budget.
The programme continues to report AMBER given the history of uncertainty around infrastructure build, and overspend on ETL Procurement. Successful completion of the TEST infrastructure build and resolution of overspend will give sufficient confidence to return to GREEN.
Status and Forward Look
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
DTI005 ETL Tool Implementation |
Planned to start Apr-18 | |
DTI021 EDW Embed & Optimise |
Planned to start Apr-18 |
|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||||
DTI004 - ETL Tool Procurement
Discretionary Milestones 15-Dec-2017 ITT Issued 28-Mar-2018 Project Delivery 13-Apr-2018 Project Close RAG RED |
Report by Nick Graham for March 2018 Achievements in Last Period
Issues
Next Steps
The project is reporting RED.
|
||||||||||
DTI006 - EDW Implementation
Discretionary Milestones 19-APR-18 Org Hierarchy ASOR 11-MAY-18 Infrastructure Build Complete 18-MAY-18 Deployment 04-JUN-18 Project Close RAG AMBER |
Report by Chris Lawford for March 2018 Achievements in Last Period
Issues
Next Steps
The project continues to report AMBER given the history of uncertainty around infrastructure build. Successful completion of the TEST infrastructure build will give sufficient confidence to return to GREEN.
|
||||||||||
DTI019 - BI/MI Analysis Toolkit
Discretionary Milestones
RAG AMBER |
Report by Sue Woodger for March 2018 Achievements
Issues
Next Steps
Project is amber as milestones are to be reviewed |
||||||||||
DTI022 - EDW Business Engagement
Discretionary Milestones 15-SEP-17 Planning Complete 24-JAN-18 Project Delivery 31-JAN-18 Project Close RAG GREEN |
Report by Geoff Cropley for March 2018 Achievements in Last PeriodAll project deliverables have been completed and handover to the business owner is underway. Project closure is expected to complete later in April. Personnel changes have extended the closure date and meetings have been arranged to confirm deliverables complete. IssuesNone to report. Next StepsContinue deliverables sign-off, handover and close project. |
Section Four: Closed or Withdrawn Projects
DTI003 Withdrawn
COM029 Proof of concept project has now been closed.