Report for June 2018
- Report Date
- June 2018
Report compiled by Chris Lawford (Programme Manager) for Alex carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Key Achievements in Last Period
- EDW LIVE build complete. “EDW Production Ready” milestone reached.
- Org/Hierarchy solution ready for deployment.
- ETL Implementation project in progress.
- EDW Embed & Optimise project initiated.
Top Issues
- Approval for proposed 18/19 budget.
- Achieving project closure on DTI019: BI/MI Analysis Tool-kit.
Key Next Steps
- Close EDW implementation project.
- Close ETL procurement project.
- Close BI/MI Analysis Tool-kit project.
Overall the programme is reporting GREEN.
Status and Forward Look
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||
DTI004 - ETL Tool Procurement
Discretionary Milestones 28-Mar-2018 Project Delivery 13-Apr-2018 Project Close RAG AMBER |
Report by Chris Lawford for June 2018 Achievements in Last Period
Issues
Next Steps
The project is reporting AMBER, in acknowledgement of the late project delivery milestone.
|
||||||||
DTI005 - ETL Tool Implementation Discretionary Milestones 02-APR-18 Project Start 20-APR-18 End of Planning 31-AUG-18 Project Delivery 14-SEP-18 Project Closure RAG AMBER |
Report by Craig Moore for June 2018 Achievements
Issues
Next Steps
|
||||||||
DTI006 - EDW Implementation
Discretionary Milestones 26-JUN-18 Infrastructure Build Complete 16-JUL-18 Deployment 03-AUG-18 Project Close and DSOR RAG GREEN |
Report by Lee-ann Simpson for June 2018 Achievements
Issues
Next Steps
The project showing as GREEN with focus continued on deployment and close of the project.
|
||||||||
DTI019 - BI/MI Analysis Toolkit
Discretionary Milestones
RAG GREEN |
Report by Sue Woodger for June 2018 Achievements
Issues
Next Steps
RAG Commentary: Project is GREEN as revised milestones approved |
||||||||
DTI021 - EDW Embed & Optimise
Discretionary Milestones RAG: Green |
Report by Lee-Ann Simpson for June 2018 Achievements in Last Period
Issues
Next Steps
The project is reporting GREEN,as the project has now been initiated and is in the planning phase. |
Section Four: Closed or Withdrawn Projects
DTI003 Withdrawn
COM029 Proof of concept project has now been closed.
DTI022 Business Engagement has now been closed.