Report for February 2017
- Report Date
- February 2017
Report compiled by Chris Lawford (Programme Manager) for Alex carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
The programme has been intiated during February 2017.
- Programme manager appointed
- Programme initiation meeting conducted (28/2)
- High Level Project plan created
- Key programme and project roles appointed
- DTI004 project kicked-off
RAG Status and Forward Look
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
---|---|
DTI004 ETL Procurement | Planned to start March |
DTI005 ETL Production |
Planned to start August |
DTI006 EDW Production | Planned to start May |
DTI007 EDW Production (embed & optimise) | Planned to start June |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary |
COM029 - EDW Proof of Concept Discretionary Milestones 24-Nov-2016 End of Planning - Proof of Concept 28-Feb-2017 Build Review - Proof of Concept Build 08-Mar-2017 Integration Review - Proof of Concept 16-Mar-2017 Delivery - Proof of Concept 24-Mar-2017 Closure - Proof of Concept RAG AMBER |
Report by Chris Copner for February 2017 Achievements in Last Period
IssuesIssue: Anticipated 20% overspend (planned spend 97d, actual spend 109d, EAC 119d). Change: Anticipating that a change to milestones will be required. This will be documented and reported to WIS once the impact is fully quantified. Reason for the change:
Next Steps
|
Section Four: Closed or Withdrawn Projects
N/A
Attachment | Size |
---|---|
capture.png | 20.15 KB |
capture33.png | 30.05 KB |