Report for September 2018
- Report Date
- September 2018
Report compiled by Chris Lawford (Programme Manager) for Alex carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Key Achievements in Last Period
- EDW Embed & Optimise project in execution phase.
- Talend Implementation, PM appointed and project in planning phase. Infrastructure architecture options under review.
- EDW budget confirmed for 18/19.
Top Issues
- EDW sustainability funding requires clarification.
Key Next Steps
- Complete project planning phase for Embed & Optimise.
- Complete planning phase for Talend Implementation.
Overall the programme is reporting GREEN.
Status and Forward Look
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
DTI005 - ETL Tool Implementation Discretionary Milestones 02-APR-18 Project Start 12-Oct-18 End of Planning 21-Dec-18 Project Delivery 18-Jan-18 Project Closure RAG Green |
Report by Jay Heer for Sept 2018 Achievements in Last Period
Next Steps
|
DTI021 - EDW Embed & Optimise
Discretionary Milestones RAG: Green |
Report by Lee-Ann Simpson for September 2018 Achievements
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
DTI003 Withdrawn
DTI004 ETL Procurement has now been closed.
DTI006 EDW Implementation has now been closed.
DTI019 BI/MI Analysis toolkit has now been closed.
COM029 Proof of concept project has now been closed.
DTI022 Business Engagement has now been closed.